Energy Impact Assessment/Statement
Energy Impact Assessment
Background The ‘Isle of Man Strategic Plan, 2016’ states:
Energy – Policy 5: ‘The Department will prepare a Planning Policy Statement on Energy Efficiency. Pending the preparation and adoption of that PPS the Department will require proposals for more than 5 dwellings or 100 square metres of other development to be accompanied by an Energy Impact Assessment. (1)
The above Policy Statement is further defined with the following:
The attached document is a suggestion of a possible format for an Energy Impact Assessment as required by Energy Policy 5 of the Isle of Man Strategic Plan.
The headings for the Energy Impact Assessment have been drawn from the following documents:
Town and Country Planning Act 1999 – Isle of Man Strategic Plan 2016 UK Communities and Local Government documents: ‘Code for Sustainable Homes – A Step-change in sustainable home building practice’ . ‘Regulatory Impact Assessment Energy Performance of Buildings Directive Articles 7-10’ BRE BREEAM Ecohomes Standards and Sustainability Checklist (including Pre-Assessment Estimator) Sustainability Checklists – Woking Borough Council Energy Saving Trust – Passive Solar Estate Layout (specifically referred to in 12.2.10 of the Strategic Plan) Town & Country Planning Association (TCPA) ‘Planning for Sustainable Energy’
| Category | Target | Notes | Achievable (YES / NO) | If YES – how? If NO – why not? | Notes |
|---|---|---|---|---|---|
| Design / Specification Energy / CO² | Improve thermal efficiency of the walls, windows and roof by eg. more insulation or better glass | Does the design specification demonstrate an improvement over currently utilised specifications / exceed current Building Regulation requirements? | Yes | Insulated Doors being fitted. Insulation exceeds Current Building Regulation Requirements for a low / unheated building where no insulation is required. | |
| Reduce air permeability – the control of fresh air into the building. | Passive Ventilation methods considered. | No | Not applicable on this scheme. | ||
| ≤1.3 Heat Loss Parameter (HLP) | Fabric of the building designed to reduce thermal bridging. | Yes | Currently exceeds Building Regulation requirements for a low heat/unheated bldg. | ||
| Reduce Energy Consumption in respect of Space Heating | • High efficiency condensing boilers – SEDBUK rating A • Alternative (oil/LPG boilers)– SEDBUK rating A • Alternative methods of heating eg. Biomass, CHP, Heat Pump • Passive Solar design Communal heating | N/A | Any heating installation will be low level under Building Regulation guidance. Heating power limited to 25W/m2. |
| Category | Target | Notes | Achievabl e (YES / NO) | If YES – how? If NO – why not? | Notes |
|---|---|---|---|---|---|
| Design / Specification Energy / CO2 | Improve thermal efficiency of the walls, windows and roof by eg. more insulation or better glass | Does the design specification demonstrate an improvement over currently utilised specifications / exceed current Building Regulation requirements? | Yes | Insulated Doors being fitted. Insulation exceeds Current Building Regulation Requirements for a low / unheated building where no insulation is required. | |
| Reduce air permeability – the control of fresh air into the building. | Passive Ventilation methods considered. | No | Not applicable on this scheme. | ||
| ≤1.3 Heat Loss Parameter (HLP) | Fabric of the building designed to reduce thermal bridging. | Yes | Currently exceeds Building Regulation requirements for a low heat/unheated bldg. | ||
| Reduce Energy Consumption in respect of Space Heating | High efficiency condensing boilers – SEDBUK rating A<br> Alternative (oil/LPG boilers)– SEDBUK rating A<br> Alternative methods of heating eg. Biomass, CHP, Heat Pump<br> Passive Solar design Communal heating<br> | N/A | Any heating installation will be low level under Building Regulation guidance. Heating power limited to 25W/m2. |
| Reduce Energy Consumption in respect of water heating | Inclusion of solar thermal water heating OR Properties to be left ‘solar enabled’ for retro-fit. | N/A | |||
|---|---|---|---|---|---|
| Improved energy efficiency of lighting (internal) | ≥75% energy efficient fixed fittings OR state %. | Yes | Metal halide and tubular fittings in accordance with table F1 Appendix F to Approved Document L2 to the Building Regs 2007. | ||
| Improved energy efficiency of lighting (external) | External lighting provided by dedicated energy efficient fittings & daylight cut-off devices. | Yes | Where appropriate, light fittings will be dedicated low energy. | ||
| Improved energy efficiency of lighting (security) | All burglar security lighting is Max. 150w & fitted with movement detecting & daylight shut-off devices. | Yes | Where appropriate, light fittings will be dedicated low energy. | ||
| Energy Efficient fixed fittings | ≥40% 0f fixed fittings – fridges and freezers have an A+ rating.<br> Washing machines and dishwashers have an A rating.<br> Washer driers & tumble driers have a B rating.<br> | No | Not applicable to this scheme. | ||
| Energy Efficient fittings (retro purchased) | Information provided to the purchaser on the benefits of purchasing energy efficient white goods where not supplied with the new Unit. | No | Not applicable to this scheme. |
| Reduce Energy Consumption in respect of water heating | Inclusion of solar thermal water heating OR Properties to be left ‘solar enabled’ for retro-fit. | N/A | |||
| Improved energy efficiency of lighting (internal) | ≥75% energy efficient fixed fittings OR state %. | Yes | Metal halide and tubular fittings in accordance with table F1 Appendix F to Approved Document L2 to the Building Regs 2007. | ||
| Improved energy efficiency of lighting (external) | External lighting provided by dedicated energy efficient fittings & daylight cut-off devices. | Yes | Where appropriate, light fittings will be dedicated low energy. | ||
| Improved energy efficiency of lighting (security) | All burglar security lighting is Max. 150w & fitted with movement detecting & daylight shut-off devices. | Yes | Where appropriate, light fittings will be dedicated low energy. | ||
| Energy Efficient fixed fittings | • ≥40% Of fixed fittings – fridges and freezers have an A+ rating. • Washing machines and dishwashers have an A rating. • Washer driers & tumble driers have a B rating. | No | Not applicable to this scheme. | ||
| Energy Efficient fittings (retro purchased) | Information provided to the purchaser on the benefits of purchasing energy efficient white goods where not supplied with the new Unit. | No | Not applicable to this scheme. |
| Reduce Energy Consumption | Provide accessible drying space (so that tumble driers need not be used). | No | Not applicable to this scheme. | ||
|---|---|---|---|---|---|
| Reduce CO2 Emissions | Provide a room or space in a quiet room, that can easily be set up as a home office. | No | Not applicable to this scheme | ||
| Reduce energy consumption | Provide FOC or for purchase or provide information – Smart Meters (visible display of energy consumption) | No | Not applicable to the scheme. | ||
| Design / Specification Water | Reduce water consumption target 120l/p/d (litres per day OR LESS (state if aiming to achieve lower) | 6/4 dual flush toilet | Yes | Dual flush mechanism installed as standard. | |
| Reduce water consumption target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | Flow reducing / aerating taps throughout. | Yes | All taps will have flow reducers. | ||
| Reduce water consumption target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | 6-9 litres per minute shower (note – average electric shower is approximately 6/7 litres per minute). | No | Not applicable to this scheme. |
| Reduce Energy Consumption | Provide accessible drying space (so that tumble driers need not be used). | No | Not applicable to this scheme. | ||
| Reduce CO2 Emissions | Provide a room or space in a quiet room, that can easily be set up as a home office. | No | Not applicable to this scheme | ||
| Reduce energy consumption | Provide FOC or for purchase or provide information – Smart Meters (visible display of energy consumption) | No | Not applicable to the scheme. | ||
| Design / Specification Water | Reduce water consumption - target 120l/p/d (litres per day OR LESS (state if aiming to achieve lower) | 6/4 dual flush toilet | Yes | Dual flush mechanism installed as standard. | |
| Reduce water consumption - target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | Flow reducing / aerating taps throughout. | Yes | All taps will have flow reducers. | ||
| Reduce water consumption - target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | 6-9 litres per minute shower (note – average electric shower is approximately 6/7 litres per minute). | No | Not applicable to this scheme. |
| Reduce water consumption target 120l/p/d (litres per day) OR LESS | 18ltr max. volume dishwasher. | No | Not applicable to this scheme. | ||
|---|---|---|---|---|---|
| Reduce water consumption target 120l/p/d (litres per day) OR LESS) | 60ltr max. volume washing machine. | No | Not applicable to this scheme. | ||
| Reduce water consumption target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | Provide a system to collect rain water for use in external irrigation / watering (eg. water butts). | No | Not applicable to this scheme. | ||
| Reduce water consumption target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | Grey Water Technology (collection and use of bath water etc. for toilet flushing). | No | Not applicable to this scheme. | ||
| Construction | Materials | Building materials sourced locally where feasible.<br> Materials from recycled sources.<br> Timber from sustainable sources.<br> Insulation materials have zero ozone depletion rate.<br> | Yes Yes Yes Yes | All materials sourced locally where appropriate. Materials are from recycled sources where appropriate. Timber is from sustainable sources where appropriate. Used as standard. |
| Reduce water consumption - target 120l/p/d (litres per day) OR LESS | 18ltr max. volume dishwasher. | No | Not applicable to this scheme. | ||
| Reduce water consumption - target 120l/p/d (litres per day) OR LESS | 60ltr max. volume washing machine. | No | Not applicable to this scheme. | ||
| Reduce water consumption - target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | Provide a system to collect rain water for use in external irrigation / watering (eg. water butts). | No | Not applicable to this scheme. | ||
| Reduce water consumption - target 120l/p/d (litres per day) OR LESS (state if aiming to achieve lower) | Grey Water Technology (collection and use of bath water etc. for toilet flushing). | No | Not applicable to this scheme. | ||
| Construction | Materials | • Building materials sourced locally where feasible. • Materials from recycled sources. • Timber from sustainable sources. • Insulation materials have zero ozone depletion rate. | Yes Yes Yes Yes | All materials sourced locally where appropriate. Materials are from recycled sources where appropriate. Timber is from sustainable sources where appropriate. Used as standard. |
| Labour | From local labour pool where feasible.<br> ‘Shared’ transport to site.<br> | Yes Yes | Local labour used where possible. ‘Crew’ transport available for ‘non-local’ labour. | ||
|---|---|---|---|---|---|
| Modern Methods of Construction (MMC) | Off-site construction. | Yes | Where feasible. | ||
| Waste | Site Waste Management to reduce / reuse / recycle waste. | Yes | Standard practice on construction sites. | ||
| Occupation | Waste | Provide recycling and storage facilities within/outside the property (multi-bin system) and/or provide an area (with bins) for recycling in line with the Government strategy (subject to inclusion of collection from the designated area by the local council/Government system). | N/A | Not appropriate as no ‘local’ collection scheme in place for recyclable waste. | |
| Waste | Provide composting facilities – for each property or communally. | No | Not applicable to this scheme. | ||
| Reduce energy & water consumption | Provide simple user guide, (non technical) for the occupier on the operation and environmental performance of their unit, including tips on how to reduce energy & water consumption. | Yes | Information to be included in ‘handover pack’. |
| Labour | • From local labour pool where feasible. • ‘Shared’ transport to site. | Yes Yes | Local labour used where possible. ‘Crew’ transport available for ‘non-local’ labour. | ||
| Modern Methods of Construction (MMC) | Off-site construction. | Yes | Where feasible. | ||
| Waste | Site Waste Management to reduce / reuse / recycle waste. | Yes | Standard practice on construction sites. | ||
| Occupation | Waste | Provide recycling and storage facilities within/outside the property (multi-bin system) and/or provide an area (with bins) for recycling in line with the Government strategy (subject to inclusion of collection from the designated area by the local council/Government system). | N/A | Not appropriate as no ‘local’ collection scheme in place for recyclable waste. | |
| Waste | Provide composting facilities – for each property or communally. | No | Not applicable to this scheme. | ||
| Reduce energy & water consumption | Provide simple user guide, (non technical) for the occupier on the operation and environmental performance of their unit, including tips on how to reduce energy & water consumption. | Yes | Information to be included in ‘handover pack’. |
| Reduce CO2 Emissions | Provide information for the occupier in respect of local alternative means of transport, cycle routes and local amenities (doctor, schools, shops etc.) | Yes | Map to be included in ‘handover pack’ highlighting local bus routes, shops etc. | ||
|---|---|---|---|---|---|
| Reduce Carbon Footprint | Inclusion of planting schemes. | No | Not applicable to this scheme. |
| Reduce CO2 Emissions | Provide information for the occupier in respect of local alternative means of transport, cycle routes and local amenities (doctor, schools, shops etc.) | Yes | Map to be included in ‘handover pack’ highlighting local bus routes, shops etc. | ||
| Reduce Carbon Footprint | Inclusion of planting schemes. | No | Not applicable to this scheme. |