25 August 2023 · Committee
Balthane Park, Balthane Industrial Estate, Balthane, Ballasalla, Isle Of Man, IM9 2ax
Permission was granted for the erection of 45 industrial, storage and distribution units in four separate blocks on vacant land between Balthane Park Industrial Estate and the New By-Pass Road at Ballasalla, Isle of Man. The applicant was Dandara Commercial Limited. The site was described as relatively level and largely bare ground, with a row of young trees along part of the western boundary and an existing electricity substation within the site. The officer report identified design and visual impact, neighbouring amenity, highway safety, and ecology as the principal planning issues. Approval was granted subject to 18 conditions. One amendment was required during the process, changing the proposed wildflower grass seed mix to a woodland wildflower mix in the interests of improved grassland and biodiversity.
The Department of Environment, Food and Agriculture approved the application on 25 August 2023. The key planning issues considered included design and visual impact, neighbouring amenity, highway safety, and ecology. An amendment to the wildflower seed mix was required as a condition, in the interests of biodiversity.
Area Plan for the South
The development complies with Employment Proposal 1
Area Plan for the South
General Policy 2
General Policy 2: Development which is in accordance with the land-use zoning and proposals in the appropriate Area Plan and with other policies of this Strategic Plan will normally be permitted, provided that the development: (a) is in accordance with the design brief in the Area Plan where there is such a brief; (b) respects the site and surroundings in terms of the siting, layout, scale, form, design and landscaping of buildings and the spaces around them; (c) does not affect adversely the character of the surrounding landscape or townscape; (d) does not adversely affect the protected wildlife or locally important habitats on the site or adjacent land, including water courses; (e) does not affect adversely public views of the sea; (f) incorporates where possible existing topography and landscape features, particularly trees and sod banks; (g) does not affect adversely the amenity of local residents or the character of the locality; (h) provides satisfactory amenity standards in itself, including where appropriate safe and convenient access for all highway users, together with adequate parking, servicing and manoeuvring space; (i) does not have an unacceptable effect on road safety or traffic flows on the local highways; (j) can be provided with all necessary services; (k) does not prejudice the use or development of adjoining land in accordance with the appropriate Area Plan; (l) is not on contaminated land or subject to unreasonable risk of erosion or flooding; (m) takes account of community and personal safety and security in the design of buildings and the spaces around them; and (n) is designed having due regard to best practice in reducing energy consumption. 6.3 Development outside of areas zoned for development
Strategic Policy 6
Strategic Policy 6: Major employment -generating development should be located in existing centres on land zoned for such purposes and identified as such in existing Local or new Area Plans. 4.4.2 To maintain a healthy and diverse economy, there needs to be sufficient land available for industrial, office and retail purposes. Accordingly:
Strategic Policy 10
Strategic Policy 10: New development should be located and designed such as to promote a more integrated transport network with the aim to: (a) minimise journeys, especially by private car; (b) make best use of public transport; (c) not adversely affect highway safety for all users, and (d) encourage pedestrian movement (1) Business Park is defined in Appendix 1 4.6 Social 4.6.1 The provision of an adequate supply of housing to meet the needs of the wider community is essential; this is in addition to the need to replace existing substandard or poor quality dwellings. Therefore;
Business Policy 1
Business Policy 1: The growth of employment opportunities throughout the Island will be encouraged provided that development proposals accord with the policies of this Plan. 9.1.3 This chapter concent rates on the land use implications of business activity, including industry, storage and distribution, office and commercial development, retailing and tourism. 9.1.4 In respect of employment land availability, the Department has undertaken and published an Employment Land Availability Study (1). A summary of this is included in Appendix 9. Across the Island there are some 118 hectares of land allocated for industrial development. Much of this is concentrated around Ballasalla and the Airport. There is, however, a spread of land available across the Island to support employment and regeneration opportunities in each area. Such land will be important to support the regeneration of the Service Centres and the Gateway and Employment role of the Airport area. 9.1.5 The Douglas area has seen by far the bulk of the industrial land take up in recent decades and much of the land allocated for such purposes has been taken up. This is why the Department has resolved to proceed with a Development Order for the development of some 20 hectares of employment land to the south of Cooil Road. A recent report on the take up of industrial land in the Douglas area indicates that it has been faster than anticipated and at current rates that all the land will be required by 2015. While the situation will be subject to detailed assessment in the preparation of the Plan for the East, the Department is satisfied that the release of additional land is both necessary and appropriate at this stage. 9.1.6 The Department has also reviewed planning permissions for office development. The majority of these are focused in the Douglas area. Take up has been low in recent years with the exception of certain relocations to corporate headquarters, such as Skandia. There are a number o f sites still available for new office development, in addition to the existing stock. Of note is the recent trend for sites with office consents to subsequently secure planning permission for residential use. The most notable example being the final pha se of the Villiers development, which now has a residential permission in addition to its partly - implemented office consent. 9.1.7 The following information has been extracted from the Review of Economic Strategy (Treasury 2003) which formed part of the background to the Economic Strategy 2004 approved by Tynwald in October that year. (1) Employment Land Availability Study DLGE 2007 9.1.8 The Isle of Man has enjoyed unprecedented economic success in the last ten years. Over this period annual gross domestic product, or GDP (the value of the economy' s output of all goods and services), has more than doubled in real terms (both absolute and per capita) such that from a deficit of around one quarter, per capita GDP in the Isle of Man now exceeds that of the UK by 7% and the average for the European Union (EU 15) by 10%. 9.1.9 The period 1993 - 2000 saw the economy not only expanding but doing so at an accelerating rate, before slowing in 2000/01. Since 2001 the economy has continued to grow at around 5% per annum (the latest national income accounts revealed growth of 5.9% in 2002/03), meaning that, after the recession in the early 1980's the Isle of Man economy has recorded economic growth in each of the last twenty years. 9.1.10 This economic performance has been led by the financial and related se rvices sectors. The finance industry grew by over 80% between 1996 and 2001 alone. But the table below illustrates that probably all areas of Manx economy are today generating more income in real terms than a decade ago, even it the relative importance o f some, most noticeably manufacturing, has declined. Table One - Sectoral Contributions to National Income 1992/93 v 2000/01 (at 2000/01 prices) Contributions to National Income (£) Real Increase in income generated (%) 1992/93 % 2000/01 % Manufacturing 72.0 11 76.7 6 6.5 Finance 229.7 35 505.4 41 120.0 Tourism 41.0 6 67.7 6 65.1 Agriculture/Fishing 11.7 2 15.8 1 35.0 Construction 46.7 7 89.6 7 91.9 Professional Services 96.7 15 186.1 15 92.4 Utilities, Distribution and Miscellaneous Services 133.1 20 223.8 18 68.1 Pubic Administration 34.6 5 53.6 4 54.9 Total 665.5 100 1,218.7 100 83.1 9.1.11 National income data aside, the clearest indication of the economic success enjoyed by the Island in recent times comes from the labour market. Census results show that the workforce increased from 33,189 in 1991 to 39,685 by 2001, an increase almost identical to that in the total resident population over the period. But the number seeking emp loyment but who were unemployed at the time halved from 1,360 to 635. 9.1.12 Changes in the underlying structure of the economy reflected in the national income accounts are further depicted in the Census statistics below showing the distribution of labour between the different sectors of the economy. Table Two - Employment by Sector 1991 v 1996 1991 1996 2001 No. % No. % No. % Agriculture and Fishing 1,240 3.9 938 2.8 543 1.4 Manufacturing 3,348 10.5 3,562 10.6 3,185 8.2 Construction 3,404 10.7 3,372 10.0 2,512 6.4 Utilities1 513 1.6 462 1.4 515 1.3 Transport and Communications 2,437 7.7 2,688 8.0 2,970 7.6 Wholesaling and Retailing 3,844 12.1 3,692 11.0 4,372 11.2 Finance 4,353 13.7 5,942 17.7 8,959 22.9 ICT2 n.a n.a n.a n.a 361 0.9 Professional Services 5,438 17.1 6,081 18.1 7,296 18.7 Tourist Accommodation 856 2.7 765 2.3 743 1.9 Entertainment and Catering 1,403 4.4 1,156 3.4 2,116 5.4 Miscellaneous Services 2,849 9.0 2,768 8.2 2,373 6.1 Public Administration 2,144 6.7 2,146 6.4 3,105 8.0 Total 31,829 100.0 33,5773 100.0 39,050 100.0 Notes: 1 Electricity, gas and water 2 Not separated out from other sectors until 2001 3 Includes 5 where occupation not recorded 9.2 Industry and Storage and Distribution 9.2.1 The nature of industrial activity on the Island changed very considerably during the last century. The previously dominant primary industries of fishing and agriculture now contribute only 1% to the Gross Domestic Product (GDP) and provide only 1.4% of our total employment, whereas manufacturing contributes 6% to the GDP and provides 8.2% of our employment, and the construction industry contributes 6% to the GDP and provides 6.4% of our employment. Storage and distribution has also become a more important activity, particularly in terms of the demands it makes on land, buildings, and access requirements. 9.2.2 Most of the Island's industry is located close to major transportation links, particularly in the case of Douglas, Braddan and Ballasalla, which all have convenient access to Ronaldsway airport and Douglas harbour. Ramsey and Peel harbours are used for the importation and exportation of large scale good s (fuel, building supplies etc). All of these are conveniently accessible to significant pools of labour. In order to minimise excessive transportation of goods and travel for employees, and to promote sustainable development, much of the Island's future industrial development should continue to be concentrated in these locations, and appropriate areas of land should be made available for such uses in the Area Plans for these parts of the Island. It will also be appropriate, when formulating Area Plans for our smaller settlements, to make provision for the continued operation of small -scale family businesses, particu
Transport Policy 7
Transport Policy 7: The Department will require that in all new development, parking provision must be in accordance with the Department's current standards. The current standards are set out in Appendix 7. 11.5.4 New development can have a significant impact in terms of the traffic generated by it and the impact on the various modes of travel. The Department considers that proposals which are likely to be significant traffic generators should be accompanied by a Transport Assessment(1) which should look at all modes of transport including access by public transport, cycling and on foot.
Strategic Policy 1
Within the adopted Isle of Man Strategic Plan 2016
Strategic Policy 1: Development should make the best use of resources by: (a) optimising the use of previously developed land, redundant buildings, unused and under -used land and buildings, and re - using scarce indigenous building materials; (b) ensuring efficient use of sites, taking into account the needs for access, landscaping, open space (1) and amenity standards; and (c) being located so as to utilise existing and planned infrastructure, facilities and services. 4.2.2 In pursuance of (c) abo ve, the Department will, when formulating its programme for the preparation of new Area Plans, have particular regard to: (a) the availability of mains drainage connected to IRIS or other mains systems; (b) securing the future viability of rural primary schools; (c) the public investment in the Island's highway, bus, railway and tramway networks; (d) the provision and availability of water; and (e) community facilities. 4.3 Environment 4.3.1
Strategic Policy 6
Within the adopted Isle of Man Strategic Plan 2016
Strategic Policy 6: Major employment -generating development should be located in existing centres on land zoned for such purposes and identified as such in existing Local or new Area Plans. 4.4.2 To maintain a healthy and diverse economy, there needs to be sufficient land available for industrial, office and retail purposes. Accordingly:
Strategic Policy 10
Within the adopted Isle of Man Strategic Plan 2016
Strategic Policy 10: New development should be located and designed such as to promote a more integrated transport network with the aim to: (a) minimise journeys, especially by private car; (b) make best use of public transport; (c) not adversely affect highway safety for all users, and (d) encourage pedestrian movement (1) Business Park is defined in Appendix 1 4.6 Social 4.6.1 The provision of an adequate supply of housing to meet the needs of the wider community is essential; this is in addition to the need to replace existing substandard or poor quality dwellings. Therefore;
General Policy 2
Within the adopted Isle of Man Strategic Plan 2016
General Policy 2: Development which is in accordance with the land-use zoning and proposals in the appropriate Area Plan and with other policies of this Strategic Plan will normally be permitted, provided that the development: (a) is in accordance with the design brief in the Area Plan where there is such a brief; (b) respects the site and surroundings in terms of the siting, layout, scale, form, design and landscaping of buildings and the spaces around them; (c) does not affect adversely the character of the surrounding landscape or townscape; (d) does not adversely affect the protected wildlife or locally important habitats on the site or adjacent land, including water courses; (e) does not affect adversely public views of the sea; (f) incorporates where possible existing topography and landscape features, particularly trees and sod banks; (g) does not affect adversely the amenity of local residents or the character of the locality; (h) provides satisfactory amenity standards in itself, including where appropriate safe and convenient access for all highway users, together with adequate parking, servicing and manoeuvring space; (i) does not have an unacceptable effect on road safety or traffic flows on the local highways; (j) can be provided with all necessary services; (k) does not prejudice the use or development of adjoining land in accordance with the appropriate Area Plan; (l) is not on contaminated land or subject to unreasonable risk of erosion or flooding; (m) takes account of community and personal safety and security in the design of buildings and the spaces around them; and (n) is designed having due regard to best practice in reducing energy consumption. 6.3 Development outside of areas zoned for development
Environmental Policy 22
Within the adopted Isle of Man Strategic Plan 2016
Environment Policy 22: Development will not be permitted where it would unacceptably harm the environment and/or the amenity of nearby properties in terms of: i) pollution of sea, surface water or groundwater; ii) emissions of airborne pollutants; and iii) vibration, odour, noise or light pollution. 7.17.2 In addition to the above, changes in the activities associated with the current permitted use of land or a building, which in themselves do not constitute development and therefore do not require planning permission, can have an adverse impact on adjacent properties by virtue of noise, light or general disturbance. For example the addition of security lig hting on a property may cause light pollution affecting adjacent properties and the wider area. The introduction of new activities into established parks and recreation areas can have an impact on neighbours. In such cases the Department would advocate t he person or organisation considering the change to give careful consideration to the potential impact of such activity in terms of location, siting and design.
Business Policy 1
Within the adopted Isle of Man Strategic Plan 2016
Business Policy 1: The growth of employment opportunities throughout the Island will be encouraged provided that development proposals accord with the policies of this Plan. 9.1.3 This chapter concent rates on the land use implications of business activity, including industry, storage and distribution, office and commercial development, retailing and tourism. 9.1.4 In respect of employment land availability, the Department has undertaken and published an Employment Land Availability Study (1). A summary of this is included in Appendix 9. Across the Island there are some 118 hectares of land allocated for industrial development. Much of this is concentrated around Ballasalla and the Airport. There is, however, a spread of land available across the Island to support employment and regeneration opportunities in each area. Such land will be important to support the regeneration of the Service Centres and the Gateway and Employment role of the Airport area. 9.1.5 The Douglas area has seen by far the bulk of the industrial land take up in recent decades and much of the land allocated for such purposes has been taken up. This is why the Department has resolved to proceed with a Development Order for the development of some 20 hectares of employment land to the south of Cooil Road. A recent report on the take up of industrial land in the Douglas area indicates that it has been faster than anticipated and at current rates that all the land will be required by 2015. While the situation will be subject to detailed assessment in the preparation of the Plan for the East, the Department is satisfied that the release of additional land is both necessary and appropriate at this stage. 9.1.6 The Department has also reviewed planning permissions for office development. The majority of these are focused in the Douglas area. Take up has been low in recent years with the exception of certain relocations to corporate headquarters, such as Skandia. There are a number o f sites still available for new office development, in addition to the existing stock. Of note is the recent trend for sites with office consents to subsequently secure planning permission for residential use. The most notable example being the final pha se of the Villiers development, which now has a residential permission in addition to its partly - implemented office consent. 9.1.7 The following information has been extracted from the Review of Economic Strategy (Treasury 2003) which formed part of the background to the Economic Strategy 2004 approved by Tynwald in October that year. (1) Employment Land Availability Study DLGE 2007 9.1.8 The Isle of Man has enjoyed unprecedented economic success in the last ten years. Over this period annual gross domestic product, or GDP (the value of the economy' s output of all goods and services), has more than doubled in real terms (both absolute and per capita) such that from a deficit of around one quarter, per capita GDP in the Isle of Man now exceeds that of the UK by 7% and the average for the European Union (EU 15) by 10%. 9.1.9 The period 1993 - 2000 saw the economy not only expanding but doing so at an accelerating rate, before slowing in 2000/01. Since 2001 the economy has continued to grow at around 5% per annum (the latest national income accounts revealed growth of 5.9% in 2002/03), meaning that, after the recession in the early 1980's the Isle of Man economy has recorded economic growth in each of the last twenty years. 9.1.10 This economic performance has been led by the financial and related se rvices sectors. The finance industry grew by over 80% between 1996 and 2001 alone. But the table below illustrates that probably all areas of Manx economy are today generating more income in real terms than a decade ago, even it the relative importance o f some, most noticeably manufacturing, has declined. Table One - Sectoral Contributions to National Income 1992/93 v 2000/01 (at 2000/01 prices) Contributions to National Income (£) Real Increase in income generated (%) 1992/93 % 2000/01 % Manufacturing 72.0 11 76.7 6 6.5 Finance 229.7 35 505.4 41 120.0 Tourism 41.0 6 67.7 6 65.1 Agriculture/Fishing 11.7 2 15.8 1 35.0 Construction 46.7 7 89.6 7 91.9 Professional Services 96.7 15 186.1 15 92.4 Utilities, Distribution and Miscellaneous Services 133.1 20 223.8 18 68.1 Pubic Administration 34.6 5 53.6 4 54.9 Total 665.5 100 1,218.7 100 83.1 9.1.11 National income data aside, the clearest indication of the economic success enjoyed by the Island in recent times comes from the labour market. Census results show that the workforce increased from 33,189 in 1991 to 39,685 by 2001, an increase almost identical to that in the total resident population over the period. But the number seeking emp loyment but who were unemployed at the time halved from 1,360 to 635. 9.1.12 Changes in the underlying structure of the economy reflected in the national income accounts are further depicted in the Census statistics below showing the distribution of labour between the different sectors of the economy. Table Two - Employment by Sector 1991 v 1996 1991 1996 2001 No. % No. % No. % Agriculture and Fishing 1,240 3.9 938 2.8 543 1.4 Manufacturing 3,348 10.5 3,562 10.6 3,185 8.2 Construction 3,404 10.7 3,372 10.0 2,512 6.4 Utilities1 513 1.6 462 1.4 515 1.3 Transport and Communications 2,437 7.7 2,688 8.0 2,970 7.6 Wholesaling and Retailing 3,844 12.1 3,692 11.0 4,372 11.2 Finance 4,353 13.7 5,942 17.7 8,959 22.9 ICT2 n.a n.a n.a n.a 361 0.9 Professional Services 5,438 17.1 6,081 18.1 7,296 18.7 Tourist Accommodation 856 2.7 765 2.3 743 1.9 Entertainment and Catering 1,403 4.4 1,156 3.4 2,116 5.4 Miscellaneous Services 2,849 9.0 2,768 8.2 2,373 6.1 Public Administration 2,144 6.7 2,146 6.4 3,105 8.0 Total 31,829 100.0 33,5773 100.0 39,050 100.0 Notes: 1 Electricity, gas and water 2 Not separated out from other sectors until 2001 3 Includes 5 where occupation not recorded 9.2 Industry and Storage and Distribution 9.2.1 The nature of industrial activity on the Island changed very considerably during the last century. The previously dominant primary industries of fishing and agriculture now contribute only 1% to the Gross Domestic Product (GDP) and provide only 1.4% of our total employment, whereas manufacturing contributes 6% to the GDP and provides 8.2% of our employment, and the construction industry contributes 6% to the GDP and provides 6.4% of our employment. Storage and distribution has also become a more important activity, particularly in terms of the demands it makes on land, buildings, and access requirements. 9.2.2 Most of the Island's industry is located close to major transportation links, particularly in the case of Douglas, Braddan and Ballasalla, which all have convenient access to Ronaldsway airport and Douglas harbour. Ramsey and Peel harbours are used for the importation and exportation of large scale good s (fuel, building supplies etc). All of these are conveniently accessible to significant pools of labour. In order to minimise excessive transportation of goods and travel for employees, and to promote sustainable development, much of the Island's future industrial development should continue to be concentrated in these locations, and appropriate areas of land should be made available for such uses in the Area Plans for these parts of the Island. It will also be appropriate, when formulating Area Plans for our smaller settlements, to make provision for the continued operation of small -scale family businesses, particu
Transport Policy 1
Within the adopted Isle of Man Strategic Plan 2016
Transport Policy 1: New development should, where possible, be located close to existing public transport facilities and routes, including pedestrian, cycle and rail routes.
Transport Policy 4
Within the adopted Isle of Man Strategic Plan 2016
Transport Policy 4: The new and existing highways which serve any n ew development must be designed so as to be capable of accommodating the vehicle and pedestrian journeys generated by that development in a safe and appropriate manner, and in accordance with the environmental objectives of this plan. 11.3.2 Notwithstanding policies within this plan which encourage travel by means other than private car it is anticipated that the number of vehicles using the Island's roads will continue to increase. This increase in demand is likely to lead to a greater need for road impro vements in order that travel can take place in a safe, effective, and environmentally acceptable manner. The Department of Transport will continue to assess the need for such improvements to public highways and undertake works where appropriate, with much of the improvement within existing roads carried out under the provisions of the Town and Country Planning (Permitted Development) Order2005. The need for improvements to the Island's highway network must be balanced against the environmental objectives of this plan.
Transport Policy 7
Within the adopted Isle of Man Strategic Plan 2016
Transport Policy 7: The Department will require that in all new development, parking provision must be in accordance with the Department's current standards. The current standards are set out in Appendix 7. 11.5.4 New development can have a significant impact in terms of the traffic generated by it and the impact on the various modes of travel. The Department considers that proposals which are likely to be significant traffic generators should be accompanied by a Transport Assessment(1) which should look at all modes of transport including access by public transport, cycling and on foot.
Condition 1
- 1. The development hereby approved shall be begun before the expiration of four years from the date of this decision notice. Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
Condition 2
- 2. Notwithstanding the meaning of development in Section 6 of the Town and Country Planning Act 1999 or any act revoking or re-enacting that Act, no mezzanine floor shall be constructed without a further application for planning approval being submitted and approved. REASON: the parking provision is considered acceptable on the basis of the floor area of the proposed units as shown in the submitted plans and on only one floor of accommodation per unit.
Condition 3
- 3. Notwithstanding the provisions of the Town and Country Planning (Use Classes) Order 2019 (or any Order revoking and/or re-enacting that Order with or without modification), the units hereby approved shall only be used for General industrial (Class 2.3) and/or Storage/distribution (Class 2.4) and for no other purpose at any time. REASON: The Department has assessed the impact of the proposal on the basis of the specific use and any alternative uses within the same Use Class will require further consideration.
Condition 4
- 4. The development hereby approved shall not be occupied or operated until the pedestrian and vehicle arrangements have been provided in accordance with the approved plan (APL_310 P4). Such areas shall remain free from obstruction thereafter and remain available to the users of the corresponding industrial unit. REASON: To ensure that sufficient provision is made for off-street parking and turning of vehicles, and pedestrian movements in the interests of highway safety.
Condition 5
- 5. The development shall be implemented strictly in accordance with the drainage plans/details referenced; ADR_500 Rev.D. No part of the development shall be occupied until the agreed drainage strategy has been implemented. The drainage system shall be permanently retained thereafter in accordance with the submitted details REASON: In order to ensure that adequate drainage/flood control measures/facilities are provided, and retained, in the interests of the amenity of the area.
Condition 6
- 6. The development hereby approved shall not be occupied or operated until the vehicle parking and turning areas have been provided in accordance with approved plans and the parking and turning areas shall thereafter be kept available for the parking and turning of vehicles associated with the development. REASON: In the interests of highway safety.
Condition 7
- 7. There shall be no obstruction to visibility splays higher than 1.05m above adjoining road level forward of a line drawn 2m back from the nearside carriageway edge at the centreline of the access extending 36m in each direction. Such visibility splays shall be provided before the construction of the buildings hereby approved is commenced and shall be permanently maintained free of obstruction thereafter. REASON: In the interests of highway safety.
Condition 8
- 8. The external cladding shall be as per drawings referenced; BSA_APL_322 P3; BSA_APL_323 P3; BSA_APL_324 P3; BSA_APL_325 P3, unless otherwise approved in writing by the Planning Authority. REASON: To ensure a uniformed high quality appearance throughout the development.
Condition 9
- 9. All planting shall be carried out in accordance with the approved details in the next available planting and seeding seasons. Any tree or shrub which within a period of 5 years from the completion of the landscaping works, is removed, or becomes seriously damaged or diseased shall be replaced in the next planting season with another similar size and species, unless the Planning Authority gives written consent to any variation. REASON: To enhance the character of the area
Condition 10
- 10. No items of machinery or any equipment or other goods shall be kept outside of any buildings and all activities shall be undertaken within the buildings unless otherwise agreed in writing by the Planning Authority. REASON: To protect the neighbouring amenity and parking areas
Condition 11
- 11. No external lighting shall be permitted except that as approved as part of a lighting scheme to be submitted to and approved by the Planning Authority. REASON: In the interest of the neighbouring amenity
Condition 12
- 12. The buildings shall be used only from Monday to Saturdays inclusive and no business shall be carried out therein on Sundays or Bank Holidays unless otherwise agreed in writing with the Planning Authority. REASON; To safeguard the character of the area
Condition 13
- 13. Noise levels from any plant, processes or equipment at the proposed industrial development measured at neighbouring residential premises including gardens, between the hours of 0700 - 2000 hrs (day-time) shall not exceed 50 dB LAeq, 1 hour; and noise levels from any plant, processes or equipment at the proposed industrial development measured at the external facade of neighbouring residential premises, between the hours of 2000 - 0700 hrs (night-time) shall not exceed 45 dB LAeq, 5 minute. REASON: To safeguard the residential amenity of the neighbouring properties.
Condition 14
- 14. All existing hedges shown on the site as being retained must, prior to the commencement of any excavation or building work on site, be protected by the erection of protective fencing. During construction no building, storage, or excavation may be undertaken within the protected areas unless authorised in writing by the Planning Authority. REASON: In the interest of the visual amenities of the area.
Condition 15
- 15. Prior to the commencement of development a boundary plan showing details of a masonry constructed wall to screen how the open spaces to the front of the parking (north) is to be secured between the buildings, shall be submitted and approved in writing by the Department. The development shall not be carried out unless in accordance with the approved details. REASON: In the interests of the character and appearance of the site and surrounding area.
Condition 16
- 16. The proposed wildflower grass seed mix as detailed on drawing referenced APL_330 RevP6, shall now use the amended see mix labelled "the woodland wildflower mix" as specified in the applicant's email of 20th June. REASON: In the interests of improved grassland and Biodiversity encouragement.
Condition 17
- 17. Prior to the occupation of any of the units hereby approved, a plan showing details and the location of the petrol and oil interceptors shall be submitted to and approved in writing by the Department. The development shall be undertaken in accordance with the approved details and maintained as such thereafter. REASON: To ensure no site pollution entering the water course.
Condition 18
- 18. Prior to the commencement of the development hereby approved a Construction Method Statement (CMS), to be provided to the Department for written approval prior to any works, including clearance and enabling works, taking place. The CMS will need to contain details of controlling any offsite pollution of the Ronaldsburn River, including sediment control measures to prevent any run off from the site during periods of adverse weather/rainfall during the construction process. The works will be carried out in accordance with the approved details. REASON: To prevent any contamination downstream of the Ronaldsburn River.
Approval in principle for development of site to create a builders and timber merchant's premises
Development of land to provide 56 Industrial Starter Units including access, parking and landscaping
Land to the south of the site has gained the following approvals for industrial units
Erection of 20 industrial units (amendment to 04/00024/B)
Land to the south of the site has gained the following approvals for industrial units
Erection of block of 12 industrial units (revision to 12/00062/B)
Land to the south of the site has gained the following approvals for industrial units
Erection of 15 industrial units in two separate blocks
Land to the south of the site has gained the following approvals for industrial units
Erection of 20 industrial units in three separate blocks
Land to the south of the site has gained the following approvals for industrial units
Erection of 20 industrial/storage units in two separate blocks
Land to the south of the site has gained the following approvals for industrial units
by-pass road, new housing and a neighbourhood centre
The land immediately to the north and north east of the application site is currently being developed
by-pass road, new housing and a neighbourhood centre
The land immediately to the north and north east of the application site is currently being developed
proposes 23 dwellings on a site which is a short distance to the north east of the application site
Recent planning application