17 February 2006 · Delegated
Ballapaddag, Cooil Road, Douglas, Isle Of Man, IM4 2af
This application sought permission to change the use of a hard standing area at Ballapaddag, Cooil Road, Douglas, Isle of Man, to allow it to be used for parking vehicles belonging to a 4WD Hire Centre. The application was decided by the Director of Planning and Building Control under delegated authority, with the case officer recommending approval. Permission was granted on 17 February 2006. The available evidence does not set out detailed planning reasons, but the proposal was considered acceptable and three conditions were attached to the permission.
The application was permitted by the Director of Planning and Building Control under delegated authority. The officer recommended approval and the decision was issued on 17 February 2006. The evidence pack does not set out detailed reasons, but the proposal was found acceptable.
Government Circular 1/06
site must include provision for a footpath link to join the site to the north allowing pedestrian access from the Main Road to the Colby Glen Road, via Site 13 and the site being developed under 11/0684/B. Advice must be sought from the Highway's Division (DoI) prior to any application being made. 5. Development plans must include ground level information and cross sectional drawings to show the relationship of any new dwellings with existing dwellings in Ballacriy Park which appear to be at a lower level than the Ballacubbon land.
Delegation of Functions to Director of Planning and Building Control
Delegation of Functions to Senior Planning Officer
Condition 1
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Condition 2
This approval relates to the submitted documents and drawings 581 001 and 581 002 all received on 23rd November 2005.
Condition 3
This approval relates to the use of the site for temporary parking for the use of the vehicles of 4WD Hire Centre for a period of 6 months from the date of this notice; at the expiry of this period, the use as a parking area must cease unless there is by that date planning approval for a further period.