Planning Approval Decision Notice
Town and Country Planning Acts, 1934 - 1991
Isle of Man Planning Scheme (Development Plan) Order 1982
Dianne Kirsten Karren Ballaconneeyn Clanna Road Santon Isle Of Man IM4 2HP
In pursuance of powers granted under the above Acts and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Dianne Kirsten Karren Proposal: Erection of a general purpose building for storage of motor caravan, garden equipment, tractor and trailer and classic cars, Ballaconneeyn, formerly at: The Warren Clanna Road Santon Isle Of Man IM4 2HP
which was considered on 14 July 2005, subject to compliance with the conditions specified below.
Date of Issue: 29th July, 2005 Murray House Mount Havelock Douglas
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the extension of the existing driveway and the erection of a general purpose building for storage of private motor vehicles and garden equipment all associated with "Ballaconneyn" (formerly "The Warren"), as show in the drawings received on 18th April, 2005.
- All external finishes to the building must be coloured dark green.
- The site must have a safe means of access and egress. As such, prior to the commencement of works on the proposed building or driveway extension, the hedges/banks on both sides of the access along the edge of the property and Clannagh Road should be lowered, such that the height of the hedge is no more than 1.05m above ground level as measured alongside the hedge.
This decision was made by the Director of Planning in accordance with powers delegated to him under Paragraph 2 (6) (b) of the Isle of Man Planning Scheme (Development Plan) Order 1982.
Note 1: This permission refers only to that required under the Town and Country Planning Acts and does not include any consent or approval under any other enactment, bylaw, order or regulation.
Note 2: No works may be commenced until such time as -
- the time for requesting a review of the initial decision has expired; or
- any review of the initial decision has been completed; or
- the time for requesting an appeal in relation to the decision has expired; or
- any appeal has been completed.
Note 3: Rights of the review of the decision are attached.