Planning Approval Decision Notice
Town and Country Planning Acts, 1934 - 1991
Isle of Man Planning Scheme (Development Plan) Order 1982
Steve Caley 13 St George's St Douglas
In pursuance of powers granted under the above Acts and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: C Bell Proposal: Erection of steel framed storage building. at: Site Opposite Tanyard House Braaid Road St. Marks Ballasalla
which was considered on 17 December 2004, subject to compliance with the conditions specified below.
Date of Issue: 29th December, 2004
Murray House Mount Havelock Douglas
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the erection of a new building attached to the existing as shown in the elevational drawing, location plan and plan reference 390/1 all received on 19th October, 2004.
- The site and building may only be used for the storage of arboricultural plant and associated equipment.
NOTE It should be noted that it is an offence under Manx legislation to permit the discharge of polluting or harmful matter to any public sewers or watercourses. Appropriate measures must be taken by the developer/user of the premises to ensure compliance with the legislation.
NOTE There must be no development within 8 metres of the watercourse to ensure habitat is retained, which may act as a wildlife corridor and also reduce disturbance to the watercourse, and decrease riverbank erosion.
This decision was made by the Planning Committee constituted in accordance with Paragraph 2 of Schedule 1 of the Isle of Man Planning Scheme (Development Plan) Order 1982.
Note 1: This permission refers only to that required under the Town and Country Planning Acts and does not include any consent or approval under any other enactment, bylaw, order or regulation.
Note 2: No works may be commenced until such time as -
- the time for requesting a review of the initial decision has expired; or
- any review of the initial decision has been completed; or
- the time for requesting an appeal in relation to the decision has expired; or
- any appeal has been completed.
Note 3: Rights of the review of the decision are attached.