3 October 2003 · Committee
Former Shelter, Shore Road, Port Erin, Isle Of Man, IM9 6hh
Permission was granted for the erection of a pair of dwellings on the site of a former shelter on Shore Road, Port Erin, in the parish of Rushen. The application was submitted on behalf of Tioman Developments Limited and was considered by the Planning Committee. The committee formally approved the application, with seven conditions attached to the permission. The decision notice was signed by the Secretary of the Planning Committee. The available evidence is limited to the decision notice itself, so detailed planning reasons behind the approval are not documented in the supplied material.
The Planning Committee approved the application by Tioman Developments Limited for a pair of dwellings on the former Shelter site on Shore Road, Port Erin. The decision was made by committee and the approval was subject to seven conditions.
Condition 1
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Condition 2
This approval relates to the following drawings $891 / 05 \mathrm{~A}, 891 / 09 \mathrm{~A}, 891 / 10 \mathrm{C}$, $891 / 11,891 / 01 \mathrm{~F}$ and location plans date stamped 20th June 2003.
Condition 3
The proposed windows to the front and side elevations shall be sliding sash, irrespective of the material used in their construction. Such opening style to be retained in perpetuity.
Condition 4
All plumbing stacks must be constructed internally.
Condition 5
The roof(s) must be finished in dark natural slate.
Condition 6
Notwithstanding the provisions of the Town and Country Planning (Permitted Development) Order 1983 (or any Order revoking or re-enacting that Order) no greenhouses, walls, gates, fences, garden sheds, garages, or tanks for the storage of oil for domestic heating shall be erected (other than those expressly authorised by this approval.)
Condition 7
Prior to the commencement of the development a plan to indicate finished floor levels must be submitted for consideration and approval by the Planning Authority.