9 July 2024 · Committee
Coroners Office, 39, Finch Road, Douglas, Isle Of Man, IM1 2pw
Permission was granted to convert Removal House, a red brick building at 39 Finch Road, Douglas, from retail use to a community facility. The site sits within a land envelope bounded by Finch Road, Christian Road, Kingswood Grove, and St Barnabas Hill. The application was submitted by Living Hope Community Church Limited. During the course of the application, amended drawings were submitted to address off-site highway works and to incorporate cycle storage facilities, a bin storage area, and their associated accesses. The committee determined to approve the application on 9 July 2024, subject to eight conditions.
The committee approved the application by Living Hope Community Church Limited to convert the building at Removal House, 39 Finch Road from retail use to a community facility. The application was approved with eight conditions and included amendments covering off-site highway works, cycle storage, bin storage, and their accesses.
Area Plan for the East
the application is considered to comply with
Strategic Plan
the application is considered to comply with
Strategic Plan
the application is considered to comply with
Strategic Plan
the application is considered to comply with
General Policy 2: Development which is in accordance with the land-use zoning and proposals in the appropriate Area Plan and with other policies of this Strategic Plan will normally be permitted, provided that the development: (a) is in accordance with the design brief in the Area Plan where there is such a brief; (b) respects the site and surroundings in terms of the siting, layout, scale, form, design and landscaping of buildings and the spaces around them; (c) does not affect adversely the character of the surrounding landscape or townscape; (d) does not adversely affect the protected wildlife or locally important habitats on the site or adjacent land, including water courses; (e) does not affect adversely public views of the sea; (f) incorporates where possible existing topography and landscape features, particularly trees and sod banks; (g) does not affect adversely the amenity of local residents or the character of the locality; (h) provides satisfactory amenity standards in itself, including where appropriate safe and convenient access for all highway users, together with adequate parking, servicing and manoeuvring space; (i) does not have an unacceptable effect on road safety or traffic flows on the local highways; (j) can be provided with all necessary services; (k) does not prejudice the use or development of adjoining land in accordance with the appropriate Area Plan; (l) is not on contaminated land or subject to unreasonable risk of erosion or flooding; (m) takes account of community and personal safety and security in the design of buildings and the spaces around them; and (n) is designed having due regard to best practice in reducing energy consumption. 6.3 Development outside of areas zoned for development
Strategic Plan
the application is considered to comply with
Environment Policy 35: Within Conservation Areas, the Department will permit only development which would preserve or enhance the character or appearance of the Area, and will ensure that the special features contributing to the character and quality are protected against inappropriate development. 7.30 Development adjacent to Conservation Areas 7.30.1 It is often the case that important views into and out of a Conservation Area can contribute significantly to its character. It is necessary to assess the impact any development adjacent to conservation areas may have on such views.
Strategic Plan
the application is considered to comply with
pment. 8.13.2 The extent of formal open space with in settlement boundaries in the South is identified on the Proposals Map (Map 3) and Inset Maps (Maps 4-7). The Isle of Man Strategic Plan (Environment Policy 42) seeks to protect these open spaces and indicates that: 8.13.3 "Inappropriate backland development, and the removal of open or green spaces which contribute to the visual amenity and sense of place of a partic ular area will not be permitted.''
Strategic Plan
the application is considered to comply with
the continued regeneration within Douglas, particularly around the Promenades and Quayside and Douglas Regeneration Area to create further housing, employment, retail and leisure opportunities. Environment Policy 43 of the Strategic Plan recognises that there are some areas showing signs of deterioration and degradation, limited investment, empty and underused buildings, derelict sites and generally poor environments. It suggests that areas that could benefit from regeneration should be identified in Area Plans and any schemes or proposals whether for refurbishment, environmental improvements or complete redevelopment must be formulated by involving the local community which would be directly affected by the regeneration of the area. Re-use of sound built fabric, rather than its demolition will be encouraged. Comprehensive Treatment Area Objectives The objectives are to: i. Optimise use of land and buildings; ii. Unlock difficult sites; iii. Assist with a co-ordinated approach to development; iv. Improve the urban environment and visual amenity; v. Encourage further investment; vi. Provide for space for Douglas Town Centre to grow; and vii. Improve access and provide better linkages. Area Plan Desired Outcomes The outcomes for each identified 'treatment area' will be tied to the proposed mix of uses on each site. The desired outcomes can be summarised under the following headings - many of which are interlinked: i. Urban Design and Integration a. To provide urban design outcomes which recognise the history of each area, their relationships to neighbouring land uses and features and takes into account appropriate transition from one land use to the next. ii. Infrastructure a. General/grey - to ensure that development staging is co-ordinated with the delivery of infrastructure and to create a road network that is permeable. b. Green - to e stablish appropriate public open space assets that are visually and physically linked via the local road network and associated pedestrian and cycling trails and waterways. To protect character in terms of landscape quality and nature conservation value with settlement boundaries. iii. Uses a. Provision of retail, community services, leisure without compromising the function and role of nearby activity centres, and which facilitates efficient and direct pedestrian, cyclist and vehicle movement. iv. Making a positive contribution a. To create an attractive urban environment that features tree -lined streets and attractive open spaces with high-amenity landscaping. v. Making the best use of resources a. Areas have been chosen because of their ability to complement existing town centres uses, and to take advantage of the roads and service infrastructure already in-place. b. To ensure balance between water quality, biodiversity, recreation and visual amenity while optimising developable land within settlement limits. vi. A more integrated transport network a. Provide realistic and workable alternatives to the use of private vehicles through the creation of direct links for pedestrians, cyclists and public transport users to town centre and retail areas, to schools, leisure facilities and other community assets. Key features of Comprehensive Treatment Areas in the East The proposals set out in this Plan: • Identify four CTAs in Douglas and one in Onchan; • Have a strong treatment focus on delivering quality urban environments, with a complementary mix of land uses and clear underlying visioning; • Translate to mapped areas without defined edges; • Describe the treatment which is proposed; and • Intend the period, within which that treatment is to begin , as being within 5 years beginning with the date on which the Plan is adopted. Proposed Comprehensive Treatment Areas in the East Comprehensive Treatment Area 1 - The Villiers (area is shown on Map 5) Despite planning approval for a variety of uses having been granted, much of the site remains undeveloped and has done for some time. The site has a negative effect on this prominent area of Douglas and impacts on the appearance of the Promenade as a whole. The area fronting the Promenade should either be developed or its appearance improved by creating an attractive public space. Re -development of the wider area would not be discounted, although where existing buildings are attractive and have a sound fabric, they should be incorporated into any wider scheme. The Central Douglas Masterplan suggests there is opportunity to support the intensification of the high street through the removal of some buildings on Duke Street. The Villiers site CTA is also a strategic freight corridor and maintaining access for commercial vehicles, including HGV's, must be considered in any proposed development. CTA Proposal 1 - The Villiers (Treatment Plan) Development of this area shall include office, leisure, retail, hotel, residential, entertainment venues, food and d rink uses and public open space or a combination thereof; or the laying out of
Strategic Plan
the application is considered to comply with
Community Policy 2: New community facilities should be located to serve the local population and be accessible to non -car users, and should where possible re-use existing vacant or underused buildings. 10.7.2 Local community facilities are important in providing for local communities without the need for travel and should be retained unless the site or premises are no longer suitable for the current or an alternative community use. Developers will be expected to demonstrate that the potential to use the site or building for other community uses has been investigated.
Strategic Plan
the application is considered to comply with
Transport Policy 7: The Department will require that in all new development, parking provision must be in accordance with the Department's current standards. The current standards are set out in Appendix 7. 11.5.4 New development can have a significant impact in terms of the traffic generated by it and the impact on the various modes of travel. The Department considers that proposals which are likely to be significant traffic generators should be accompanied by a Transport Assessment(1) which should look at all modes of transport including access by public transport, cycling and on foot.
Conservation of the Historic Environment
the application is considered to comply with
Condition 1
The development hereby approved shall be begun before the expiration of four years from the date of this decision notice.
Condition 2
The approved use is community facilities within Class 4.3 of the Use Class Order 2019 (and any legislation that may precede or replace this order).
Condition 3
Prior to the occupation or operation of the community facility hereby approved, the off-site highway works on the west side of Finch Road that are also south of St Barnabas Hill, including the drop-off/pick up bay fronting the site, one dropped curb and all other highway works within red line of application, as detailed in the approved plan (drawing no. P-03, which was received on 10th May 2024) must be completed and retained thereafter.
Condition 4
Prior to the occupation or operation of the community facility hereby approved, the cycle storage facilities, bin storage area and their accesses shown in the approved plan (drawing no. P-01 Rev E, which has been received on 10th May) must be completed and retained thereafter.
Condition 5
The materials and finishes used in the renovation must match those specified in the approved plans. Reason: To preserve the character and appearance of the Windsor Road Conservation Area.
Condition 6
Prior to the removal of the fountain on the east boundary, as shown in drawing no. P-02 Rev D, which was received on 10th May 2024, details of the existing fountain shall be documented submitted to the Department.
Condition 7
No development shall take place until full details of hard landscaping works have been submitted to and approved in writing by the Department and these works shall be carried out as approved. The hard landscaping should include details of the surface finishes of the front paving and footpaths as well as any new walls to all boundaries of the site, including details of the repositioned fountain/font. The hard landscaping works, including the repositioned fountain/font shall be completed in full accordance with the approved details prior to the first use of the occupation or operation of the community facility hereby approved. Reason: To safeguard existing positive features of the site.
Condition 8
Prior to the occupation or operation of the community facility hereby approved, disability access ramps, as shown in drawing no. P-02 Rev D, which was received on 10th May 2024, shall be installed and retained thereafter.