21 January 2025 · Delegated
Wrights Pit North Landfill Off, Cranstal Road, Bride, Isle Of Man, IM7 4bs
This application sought to extend the time allowed for landfilling operations at Wrights Pit North, a 4.15-hectare site at Point of Ayre in the north of the Isle of Man, until 31 December 2030, with a further year to complete restoration by 31 December 2031. It also proposed adding a new waste type — non-hazardous dredged material from ports, harbours, and flood risk management works — to those permitted at the site. The site sits to the east of a designated Area of Special Protection for Birds and has a history of previous planning applications. The officer's report identified the key planning issues as whether there remained a continued need for the landfill, whether adding the new waste type would affect efficient use of remaining void space, the environmental and amenity impacts of continued operation, and the implications for final restoration. The case officer recommended the application for approval. However, the application was formally withdrawn on 21 January 2025, so no planning permission was granted or refused.
The application was withdrawn by the applicant on 21 January 2025. Although the case officer had recommended approval, no formal decision was issued. The withdrawal means no permission was granted or refused.
Waste management installations, including landfill sites
Strategic Plan (2016)
Extend the time for landfill operations for a further five years plus one year to enable the restoration scheme to be completed, importation of c.5000 tpa of mixed inert and C&D wastes over the five year period and development of an amended alternative restoration scheme to reflect the projected volume of imported materials
most relevant
Variation of condition 2 of application 12/01671/B for the continued deposit of inert and mixed construction/demolition waste and associated site restoration, to extend the approval for a further 12 months
Installation of 16 groundwater monitoring boreholes at Current And Former Landfill Site, Cranstal, Bride
Extend the time for landfilling operations to continue until 31st December 2030, plus 1 year to enable the restoration scheme to be completed by 31st December 2031
Construction, operation and decommissioning of a temporary lagoon facility for dewatering and storing sediment dredged from Peel Marina and installation, operation and removal of temporary pipelines along and alongside the River Neb between Ballaterson Farm and Peel Marina