Miss Dawn Winn 3 Kermode Close Crosby IM4 4BS
TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure) Order 2019
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Mr Sam Colburn, Ref 24/00466/B, for the Renovation of cottage and outbuilding to include alterations to window/door openings, creation of a detached garage/store, erection of wall for privacy and new vehicular access with associated driveway and parking area at The Barn Bollyn Road Ballaugh Isle Of Man IM7 5AY .
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
Reason: In the interests of the character and appearance of the development and to ensure that the finished appearance of the development will enhance the character and visual amenities of the area.
and surfaced in accordance with the details shown on the approved plans (Drawing Nos. 02P and 04P). Once provided, all access, parking and turning areas shall thereafter be permanently retained as such.
Reason: To ensure the provision of a means of access, parking and turning space to an adequate standard in the interests of road safety.
Reason: In the interests of the character and appearance of the development and to ensure that the finished appearance of the development will enhance the character and visual amenities of the area.
Plans and Drawings: This approval relates to the following plans and documents:
Structural Assessment Received 22 August 2024.
NOTE FOR YOUR INFORMATION Please be aware that a ban on the installation of fossil fuel heating systems in any new building(s) and or extension(s), will come into force on 1st January 2025.
You therefore are encouraged to ensure that your proposed development includes alternatives to fossil fuel heating systems if you believe that such works will not be completed by that date.
To this end, if you propose an alternative, such as air source or ground source heat pump(s), or any other heating system that would require planning approval, the details of this should be addressed now. This may require you to resubmit your planning application to accommodate the alternative permitted heating system proposed.
This decision has been made for the following reasons(s) Overall, the proposal is considered to accord with General Policy 3, Housing Policy 11, Environment Policies 1 and 2, Transport Policies 4 and 7, and General Policy 2 the IOM Strategic Plan. No unacceptable adverse impact has been identified as likely with respect of the character and appearance of the existing building and surrounding landscape, the residential amenity of the neighbouring property or on parking and highway safety.
Date of Issue: 3rd September 2024
J CHANCE Director of Planning and Building Control
Guidance Note This decision was made by the Planning Committee in accordance with the authority delegated to it. This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.
A copy of the Officer’s report and any correspondence which led to the assessment and decision is available to view on the Government’s website (via Online Services www.gov.im/Viewapplications) or at the Department’s offices Murray House, Mount Havelock, Douglas.
Implementation The decision does not become final until either Any appeal has been concluded; or 21 days have passed since the date on this notice and no appeal has been submitted
Development must progress in accordance with the plans approved under, and any conditions attached to this approval (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Appeal Any appeal must be in writing and submitted to the Department within 21 days of the date of this Notice. The appeal must contain: the grounds for making the appeal; payment of the planning appeal fee (currently £355); and
if relevant, confirmation that the appellant wishes to have the appeal determined by means of an inquiry and payment of the additional inquiry fee (currently £130). Where the appeal is submitted by the applicant they must:
specify in detail and by reference to material planning considerations the reasons why the appellant disagrees with that determination; and
Where against a refusal, on the grounds of deficient detail or supporting documentation, set out why they consider the information or documentation forming part of the application was sufficient in the circumstance. If the appeal is submitted by someone who has interested Person Status but is not listed in Article 4(2) of the Development Procedure Order 2019, that person must relate their grounds for making the appeal to issues which they included in representations made prior to the application being determined.
Failure to meet all of the relevant above requirements will mean that the appeal cannot be validated. An appeal form and more detailed guidance are available either from Planning & Building Control, Tel 685950, or from the Department’s website www.gov.im/planningappeal If this decision becomes final because there is no appeal, the Department’s public reference copy (counter copy) of the planning application (should one have been received) may be collected by the applicant or their agent from Murray House. Please note that if the counter copy of the application is not collected within thirty days following the last date on which a planning appeal can be made it will be destroyed without further notice.