4 September 2020 · Delegated
Proposed Fire Pump House, Mill Road, Peel, Isle Of Man, IM5 1tb
The application sought permission to replace two existing cylindrical fire water storage tanks on a site off Mill Road, Peel, close to the River Neb to the west and residential properties at Close Chiarn to the south. The existing tanks are 7 metres high and 7 metres wide and sit within a reinforced masonry bunded perimeter wall approximately 2 metres high. The replacement tanks would occupy the same bunded area at the same scale and form as the existing structures. The key planning issues were whether the development was appropriate for its land-use designation, whether it posed any flood or environmental risk given its proximity to the River Neb, and whether it would harm the amenity of nearby residents. DEFA Inland Fisheries sought clarification on the proximity to the watercourse; the applicant confirmed that all works would remain within the bunded area with no works in or to the river. The officer concluded that the scale, level, and form of the replacement tanks were appropriate and that the proposal would not harm neighbouring properties or the wider environment.
The replacement tanks are like-for-like in scale and position within the existing bunded enclosure, making the development consistent with the land-use designation. No works would affect the adjacent River Neb, and no harm to neighbouring amenity, flood risk, or environmental quality was identified. The proposal was found to comply with General Policy 2, Environment Policies 10 and 22, and Energy Policy 1.
General Policy 2
Development which is in accordance with the land-use zoning
General Policy 2: Development which is in accordance with the land-use zoning and proposals in the appropriate Area Plan and with other policies of this Strategic Plan will normally be permitted, provided that the development: (a) is in accordance with the design brief in the Area Plan where there is such a brief; (b) respects the site and surroundings in terms of the siting, layout, scale, form, design and landscaping of buildings and the spaces around them; (c) does not affect adversely the character of the surrounding landscape or townscape; (d) does not adversely affect the protected wildlife or locally important habitats on the site or adjacent land, including water courses; (e) does not affect adversely public views of the sea; (f) incorporates where possible existing topography and landscape features, particularly trees and sod banks; (g) does not affect adversely the amenity of local residents or the character of the locality; (h) provides satisfactory amenity standards in itself, including where appropriate safe and convenient access for all highway users, together with adequate parking, servicing and manoeuvring space; (i) does not have an unacceptable effect on road safety or traffic flows on the local highways; (j) can be provided with all necessary services; (k) does not prejudice the use or development of adjoining land in accordance with the appropriate Area Plan; (l) is not on contaminated land or subject to unreasonable risk of erosion or flooding; (m) takes account of community and personal safety and security in the design of buildings and the spaces around them; and (n) is designed having due regard to best practice in reducing energy consumption. 6.3 Development outside of areas zoned for development
Environment Policy 10
flood risk assessment
irements of the relevant gas supply agency. Flood Risk 63 There was widespread concern about the adequacy of drainage and the risk of flooding, particularly in parts of Braddan, Onchan and Laxey. Environment Policy 10 of the Strategic Plan indicates that where development is proposed on any site where there is a potential risk of flooding, the prospective developer will be required to submit a flood risk assessment, together with details of proposed mitigation measures. This approach is reinforced in Utilities Proposal 6 of the draft Area Plan, which (among other things) requires the incorporation of Sustainable Drainage Systems (SuDS) into new developments, to attenuate the rate of surface water run-off. I consider these policies to be reasonable. Clearly, without adequate mitigation measures, new building should normally be resisted on land which is at serious risk of flooding, or where the proposed development would increase the flood risk elsewhere. 64 In my view, the format of Utilities Proposal 6 could be improved. First, as a Proposal of the Area Plan, I consider that it should be in a bold typeface, to differentiate it from the supporting text. (The same applies to a number of other policies e.g. Transport Policy 2, and Utilities Policies 2 and 5). Second, there appears to be an error of syntax at the start of the second sentence of Utilities Proposal 6, which should perhaps read 'Strategies to achieve this will include …'. Third, the third bullet point of this Proposal introduces SuDS. Subsequent bullet points describe features of SuDS, and are therefore subordinate to the third bullet point. For clarity, I consider that they should be indented. I recommend that the draft Area Plan be modified accordingly. Sewage Treatment 65 There was also some public concern about the adequacy of the sewerage system, both in terms of its capacity to accommodate the effluent from proposed residential development areas, and in terms of the current practice of discharging untreated sewage into the sea. Infrastructure Policy 1 of the Strategic Plan indicates that developments entailing the erection of multiple dwellings should take place only on sites that will ultimately be connected to the IRIS system, which takes sewage to a treatment works at Meary Veg. (IRIS is an acronym for Integration and Recycling of the Island's Sewage). However, as long ago as 2006/7, a review was undertaken to decide whether to continue with the IRIS strategy. This concluded that it would be beneficial to adopt a regional sewage treatment strategy (RSTS) for those settlements that were not already connected to the IRIS system, including Laxey, Baldrine and settlements in the Central Valley. To that extent, Infrastructure Policy 1 of the Strategic Plan is now out of date. 66 I understand that a planning application will soon be submitted for the development of a local sewage treatment facility for Laxey. Feasibility studies for the provision of a similar facility to serve Baldrine are ongoing. A replacement sewage works at Ballagarey, serving part of the Central Valley became operational in 2018. However, capacity limitations mean that planned development in Crosby is likely to have to rely on standalone sewage treatment for the time being, until the existing treatment works is replaced as anticipated in 2022. The Programme for Government (2016-2021) indicates an intention to complete the regional sewage treatment infrastructure within the lifetime of the present administration. 67 It seems to me that these considerations should be taken into account in the allocation and phasing of land for development. I will return to this matter when considering the draft Area Plan's proposals for housing. Electricity Renewable Energy 68 Peel Energy considered that the Area Plan should contain a detailed and specific chapter on renewable energy, providing measurable criteria against which applications for the development of renewable power generating facilities would be assessed. They cited the States of Jersey Island Plan 2011, which includes such material. And they pointed out that a Climate Change Emergency has recently been declared on the Isle of Man; that a Climate Change Bill is soon to be presented to Tynwald; and that there has been strong public support for the Government's Climate Change Mitigation Strategy. They argued that, in failing to provide detailed guidance on renewable power generation, the Area Plan was inconsistent with the Strategic Plan; and that since the Area Plan post-dated the Strategic Plan, its largely negative provisions would prevail. 69 Energy Policy 4 of the Strategic Plan applies to development proposals for renewable energy generated by wind, water, tidal or solar power. It indicates that any such proposals will be judged against that Plan's environmental objectives. Proposals for wind, water or tidal power would need to be supported by an Environmental Impact Assessment. The supporting text indicates that renewable energy schemes will be given similar scrutiny as is gi
Environment Policy 22
Development will not be permitted where it would unacceptably harm the environment
Environment Policy 22: Development will not be permitted where it would unacceptably harm the environment and/or the amenity of nearby properties in terms of: i) pollution of sea, surface water or groundwater; ii) emissions of airborne pollutants; and iii) vibration, odour, noise or light pollution. 7.17.2 In addition to the above, changes in the activities associated with the current permitted use of land or a building, which in themselves do not constitute development and therefore do not require planning permission, can have an adverse impact on adjacent properties by virtue of noise, light or general disturbance. For example the addition of security lig hting on a property may cause light pollution affecting adjacent properties and the wider area. The introduction of new activities into established parks and recreation areas can have an impact on neighbours. In such cases the Department would advocate t he person or organisation considering the change to give careful consideration to the potential impact of such activity in terms of location, siting and design.
Energy Policy 1
Proposals for the provision of energy supply facilities
Condition 1
The development hereby approved shall be begun before the expiration of four years from the date of this decision notice.
Condition 2
The existing two tanks shall be removed from the site within 6 months of the proposed tanks being completed.