Loading document...
Partington Nixon & Kinrade 7-9 Drinkwater Street Douglas IM1 1AT
In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: A V Craine & Sons Proposal: Extension to and continued use of existing stone quarry at: Cringle Quarry Ronague Castletown Isle of Man IM9 4HJ
which was considered on 16th January 2009, subject to compliance with the conditions specified below.
Date of Issue: 22nd January 2009 Murray House Mount Havelock Douglas
Deputy Secretary Planning Committee
a) a scheme for monitoring of the impact on wildlife throughout the development, including the reporting of species of importance and the action to be taken in this respect, b) a scheme for the undertaking of appropriate management to enhance other areas of heathland around the quarry based upon the operational life of the quarry c) a detailed scheme for the monitoring of the water level in the pond indicating who is to monitor this and the steps to be taken if levels are affected adversely by the proposed quarry extension.
a) demonstrate that there will be no increase in the amount of water flowing onto the highway from the quarry and b) demonstrate that the water being discharged from the quarry, through the phased life of the quarry working and thereafter from the proposed pond will be dealt with satisfactorily, particularly the discharge of any water from the new pond in the quarry floor to the existing outlet.
The applicant is recommended to discuss both of the above with the Department of Transport Drainage Division prior to the submission of any further information.
This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
Whichever is the later.