Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Quay Design Ltd. 5 The Quay Port St Mary IM9 5EA
In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Mr & Mrs D Turner Proposal: Erection of a dormer extension to east elevation at: 1 Ballakeyll Colby Isle of Man IM9 4AY
which was considered on 7th December 2007, subject to compliance with the conditions specified below.
Date of Issue: Murray House Mount Havelock Douglas
Deputy Secretary Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This permission relates to the alterations and extensions shown in drawing 1329-01 received on 17th September, 2007.
NOTE The Chief Fire Officer recommends the installation of mains wired interconnected domestic smoke detection.
NOTE The applicant is advised that there are Underground Cables/Overhead Lines present in the area indicated in the planning application. Please contact Anthony Kinrade or Ian Horsey, Operations and Maintenance Department, Network Services, Manx Electricity Authority, (Tel.
687687) to discuss working practices around Cables and Overhead Lines which may be required to be diverted before any work can be carried out on site.
The applicant is also advised to contact the Manx Electricity Authority for Electrical Site Safety 5 documents, (Tel. 687766), before any work is carried out on site. All work to be carried out with reference to Health and Safety Executive Guidance Notes HS(G)47 and GS6.
This decision was made by the Director of Planning and Building control in accordance with the authority delegated to him under Article 3(13) of the Town and Country (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/dlge/planning/plan/applications/decision.xml
Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.