Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Mr & Mrs K Baker Kyrenia Mines Road Foxdale Isle Of Man IM4 3ET
In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Mr & Mrs K Baker Proposal: Extension to rear of existing detached garage at: Kyrenia Mines Road Foxdale Isle Of Man IM4 3ET
which was considered on 24th September 2007, subject to compliance with the conditions specified below.
Date of Issue: 26th September 2007
Murray House Mount Havelock Douglas
Deputy Secretary Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This permission relates to the plans and information 2007/10/01, 2007/10/02, 2007/10/03, 2007/10/04, 2007/10/05 as submitted and date stamped 17th July 2007.
- The external finishes of the extension must match those of the existing building in all respects.
- The extended garage hereby permitted by this approval shall only be used for purposes ancillary to the enjoyment of the associated dwelling "Kyrenia".
- There must be No discharge of surface water (including that from roofs and paved areas) from this proposed development to any foul drainage system(s) so as to comply with the requirements of the Department of Transport Drainage Division and the Sewerage Act 1999.
The application states that the surface water from the proposed development is to be discharged to the "existing drainage". If this "existing drainage" discharges (directly or indirectly) to the foul sewerage system then it should be noted that an alternative means of surface water disposal must be provided.
Written permission must be obtained from any third party property owners for permission to build over the private drain which runs through the site.
NOTE There are Underground Cables/Overhead Lines present in the area indicated in you Planning Application. Please contact our Network Operations Department, Manx Electricity Authority, (Tel. 687687) to discuss working practices around Cables and Overhead Lines which may be required to be diverted before any work can be carried out on site.
Contact the M.E.A. for Electrical Site Safety 5 documents, (Tel. 687766), before any work is carried out on site. All work to be carried out with reference to Health and Safety Executive Guidance Notes HS(G)47 & GS6.
This decision was made by the Director of Planning and Building control in accordance with the authority delegated to him under Article 3(13) of the Town and Country (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/dlge/planning/plan
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.