Planning Approval Decision Notice
Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Mr M J C Quaye Upper Ballacrye Sandygate Ramsey Isle of Man IM7 3BS
In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Mr M J C Quaye Proposal: Erection of an agricultural building at: Field 214380 Upper Ballacrye Sandygate Ramsey Isle of Man IM7 3BS
which was considered on 1 May 2007, subject to compliance with the conditions specified below.
Date of Issue: 4 May, 2007 Murray House Mount Havelock Douglas Secretary Planning Committee (Signature)
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the submitted documents and drawings 00240/1 and 3563-01 all received on 7th February 2007.
- The building must only be used for agricultural purposes.
- Prior to the commencement of any works, there must be submitted to and approved samples of the roof and wall sheeting.
NOTE There are Underground Cables/Overhead Lines present in the area indicated in you Planning Application. Please contact our Network Operations Department, Manx Electricity Authority, (Tel. 687687) to discuss working practices around Cables and Overhead Lines which may be required to be diverted before any work can be carried out on site.
Contact the M.E.A. for Electrical Site Safety 5 documents, (Tel. 687766), before any work is carried out on site. All work to be carried out with reference to Health and Safety Executive Guidance Notes HS(G)47 & GS6.
This decision was made by the Director of Planning and Building control in accordance with the authority delegated to him under Article 3(13) of the Town and Country (Development Procedure) Order 2005.
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/dlge/planning/plan
Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later. Applicant/Agent