Loading document...
Application No.: 15/01148/B Applicant: Department Of Infrastructure Proposal: Demolition of existing dwellings and erection of replacement dwellings and apartments with associated car parking, roads and footpaths, landscaping and drainage Site Address: Clagh Vane Estate Ballasalla Isle Of Man IM9 2HE Case Officer : Miss S E Corlett Photo Taken: 05.11.2015 Site Visit: 05.11.2015 Expected Decision Level: Planning Committee
1.1 The site is part of the Clagh Vane residential estate which lies on the northern side of the A5 Douglas to Castletown Road. The estate is mainly public sector housing managed by the Department of Infrastructure. The estate is in the process of a scheme of renovation, enhancement and replacement which has seen the introduction of brand new units close to the main road of a modern and striking form, the upgrading of other properties together with reorganisation of parking areas and gardens. One part of the scheme proposed the erection of new dwellings on a former play area to the north east of the application site. This proposal, PA 13/91443/B proposed the erection of dwellings on the former playground which had been used as a site compound and the development was approved subject to a condition which read:
"The area shown on plan reference 11A, currently accommodating numbers 69, 71, 73, 75 and 77, Clagh Vane, or equivalent approved by the Planning Authority, must be set out and available for use as Public Open Space within twelve months of the date of the first occupation of any of the dwellings hereby approved."
1.2 These units are largely complete. - 1.3 The application site comprises numbers 2-44 (evens only) and 37 - 79 (odds only) Clagh Vane, arranged in a horse shoe shape with the central area occupied by the even numbered dwellings. Other than numbers 20, 22, 24, 26, 28 and 30, the houses are all two storey arranged in pairs, rows of three and terraces of four all with dashed rendered walls and tiled roofs. None of the properties has on site car parking and there is on-street parking available and within the centre of the horse shoe shape where the space is all hard surfaced and car parking spaces laid out. This is not particularly attractive, nor is it landscaped. - 1.4 There are a number of trees within the existing layout of various types, many close to existing buildings and others contributing to the overall streetscene with the various hedges and shrubs. THE PROPOSAL
2.1 Proposed is the demolition of the 42 existing properties and their replacement with 51 new units arranged in rows with plots 69, 71, 73, 75 and 77 left open as public open space. The dwellings are two storey, finished in self coloured render and with slate effect roofing. Each has a small front garden and larger rear private space bounded by walls and railings. Public open space will be
3.1 The site lies within an area designated on the Area Plan for the South adopted in 2013 as Residential. There are various references to the estate and the on-going renovation works there. - 3.2 As such, the development should accord with the general standards of development as set out in General Policy 2 as follows:
"Development which is in accordance with the land use zoning and proposals in the appropriate Area Plan and with other policies of this Strategic Plan will normally be permitted, provided that the development:
3.3 The Strategic Plan also requires that affordable housing is provided at a rate of 25% of new units proposed and that public open space is provided (see paragraph 2.2 above). These amounts should be applied to the net increase of units (ie 9 new units) as the majority of the housing proposed replaces units which are already there. The housing is all administered as public sector housing. PLANNING HISTORY - 4.1 Clagh Vane has been the subject of a number of applications for regeneration and redevelopment, none of which is particularly relevant to the current proposal, other than that for the former play area referred to in paragraph 1.1 above. REPRESENTATIONS - 5.1 Malew Parish Commissioners indicate that they have no objection (05.11.15).
5.2 Department of Infrastructure Highway Services have requested a deferral pending their input (11.11.15) but have indicated verbally that they have no issues with the scheme (19.11.15). ASSESSMENT - 6.1 The scheme represents an onward regeneration and improvement of the estate, both aiming to enhance the visual character of the estate but also the provision of more appropriate levels of car parking and public open space and ensuring that the housing meets today's standards of accessibility and designing out crime. The Department of Infrastructure is also aware of the need and policy requirement to optimise the development of sites as set out in Strategic Policy 1 and paragraph 4.13.2 of the Area Plan which states:
"To this end, the Department will ensure that a density level on the sites is realised which makes best use of the available land and seeks to optimise the number of dwellings on the site. This should not be taken to be an opportunity to seek maximisation of the site much more a considered approach to ensuring that the best use is made of the site taking full consideration of all material considerations."
6.2 The dwellings will be set out with adequate levels of amenity space, both public and private and with more convenient and better laid out car parking opportunities. Drainage will be enhanced, reducing the amount of surface water discharging unmodified to the system.
6.3 A landscaped area is to be introduced in front of the southernmost houses beyond which will be the gables of the houses.
6.4 The scheme will complement the work already done within Clagh Vane which is gradually upgrading not only the appearance of the area but also the levels of amenity - car parking and outlook for the residents and making better use of the available building land. The application is therefore considered to be acceptable and is recommended for approval. - 6.5 The timely delivery of the public open space is essential to the success of the scheme and its accordance with the Strategic Plan. Whilst the public open space was required to be provided and available for use within 12 months of the occupation of the first dwelling within the earlier housing development, the construction of the development now proposed is likely to take longer than that (November 2016) and as such, the applicant has queried whether it would be possible to defer completion and use of the play area until a later date. They would like this time period to be somewhere in the region of 12 months after the completion of the present development but would suggest that if this is too long a period, perhaps the public open space could be required to be completed and available for use by the time half of the houses hereby approved are completed.
7.1 By virtue of the Town and Country Planning (Development Procedure) (No 2) Order 2013, the following persons are automatically interested persons:
With effect from 1 June 2015, the Transfer of Planning & Building Control Functions Order 2015 amends the Town and Country Planning Act 1999 to give effect to the meaning of the word 'Department' to be the Department of Environment, Food and Agriculture unless otherwise directed by that Order.
Recommendation Recommended Decision: Permitted Date of Recommendation:
20.11.2015
Reason: To comply with article 14 of the Town and Country Planning (Development Procedure) (No2) Order 2013 and to avoid the accumulation of unimplemented planning approvals.
All planting, seeding or turfing comprised in the approved details of landscaping must be carried out in the first planting and seeding seasons following the completion of the development or the occupation of the dwellings, whichever is the sooner. Any trees or plants which within a period of five years from the completion of the development die, are removed, or become seriously damaged or diseased must be replaced in the next planting season with others of a similar size and species.
REASON: the landscaping of the site is an integral part of the scheme and must be implemented as approved.
Reason: to ensure that the development has adequate levels of public open space in accordance with the Strategic Plan and to accord with that earlier decision.
This approval relates to drawings 01, 02D, 03, 04, 06, 07, 08, 09, 10A, 11, 16, 17, 18A, 21, 22, 23, 24, 7_300_P1, 7_301_P1, 7_302_P1, 7_303_P1, 7_304_P1, 7_305_P1, 7_306_P1, 7_307_P1, 7_308_P1 and PL397/02A all received on 14th October, 2015.
I confirm that this decision has been made by the Planning Committee in accordance with the authority afforded to it under the appropriate delegated authority.
Signed :……M McKNIGHT…………….. Presenting Officer
Further to the decision of the Committee an additional report/condition reason was required (included as supplemental paragraphin the Officer’s report).
Signatoryto delete as appropriate YES/NO