Planning Approval Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
M P Associates Ltd<br>12 Strathallan Crescent<br>Douglas<br>Isle of Man<br>IM2 4NR
In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Proposal: at:
Carlton Homes Ltd Alterations and extensions to dwelling Fern Glen Cottage Glen Auldyn Ramsey Isle of Man IM7 2AG which was considered on 11th June 2009, subject to compliance with the conditions specified below.
Date of Issue: 24th June 2009
Murray House <br> Mount Havelock <br> Douglas
Deputy Secretary Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the alterations and extensions to dwelling as proposed in the submitted documents and drawing 0790/PL01 all received on 17th February 2009.
- The roof(s) must be finished in dark natural slate.
- Prior to the commencement of works a method statement is required to be submitted to and agreed in writing by the Planning Authority in consultation with the Inland Fisheries Development Manager; stating precautionary measures to be taken to prevent pollution /
sedimentation of the watercourse and damage to bankside habitats and species. Such measures are to be implemented during and post construction of the development.
NOTE No permission is granted or implied to the reconstruction of the dwelling should it prove to be unstable. 28
This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.