31 January 2014 · Delegated
The Old Rectory, Station Road, Ballaugh, Isle Of Man, IM7 5ah
This application sought approval in principle to divide the residential plot at The Old Rectory, Station Road, Ballaugh into two separate plots, with a new dwelling to be built on the newly created plot using the existing driveway for access. The application was determined under delegated powers and approved in principle on 31 January 2014. The decision was subject to compliance with eight conditions, though the detail of those conditions is not available in the supplied evidence. The formal decision record lists 8 conditions.
The Department of Infrastructure approved this application in principle, subject to eight conditions. The decision was made under delegated powers and signed off by M. Gallagher.
Condition 1
Approval of the details of siting, design, external appearance of the building, internal layout, landscaping of the site (hereinafter called "the reserved matters") shall be obtained from the Planning Authority in writing before any development is commenced.
Condition 2
The application for approval of the reserved matters shall be made to the Planning Authority before the expiration of two years from the date of this permission.
Condition 3
The development to which this permission relates shall begin within 4 years of the date of this permission or within two years of the final approval of the reserved matters, whichever is the later.
Condition 4
This approval is in principle only and relates to the erection of one dwelling within the land defined by the red line on Location Site Plan received on 16th December 2013.
Condition 5
The application for the reserved matters must demonstrate that two off street parking spaces are provided in accordance with the Isle of Man Strategic Plan 2007.
Condition 6
The application for Reserved Matters must include a full landscaping scheme of the site including the canopy spread of the existing trees on the site.
Condition 7
The application for Reserved Matters must include a scheme which demonstrates how trees on the site are to be protected during construction works. The scheme must include a drawing which shows how tree roots are to be protected and development must take place only in accordance with the approved scheme of protection.
Condition 8
There must be no glazing installed on the south eastern elevation.