Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Isle of Man Water & Sewerage Authority
Drill Hall
Tromode
Douglas
IM2 5PA
In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Infrastructure does hereby APPROVE the following application made on behalf of:
Name: Isle of Man Water & Sewerage Authority Proposal: Construction of a service reservoir and creation of temporary track and access at: Field 132382 Glen Auldyn Ramsey Isle of Man which was considered on 2nd September 2010, subject to compliance with the conditions specified below. Date of Issue: 6th September 2010 Murray House Mount Havelock
Douglas
Mr. P. Faragher
Deputy Secretary to the Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the construction of a service reservoir and creation of temporary track and access as proposed in the submitted documents and drawings 1000D, 4001B, 2A, 3B, 4B, 1002, 10, 15, 13/9/01TW all received on 25th June 2010.
- On completion of the Service Reservoir the temporary haul route, the upgraded entrance onto the Glen Auldyn Road and the temporary site compound are to be removed and reinstated to their original condition.
- The Service Reservoir roof is to be finished with top soil and then grassed. All planting shall be carried out in accordance with the approved details in the next available planting and seeding seasons. Any tree or shrub which within a period of 5 years from the completion of the landscaping works, is removed, or becomes seriously damaged or diseased shall be replaced in the next planting season with another similar size and species, unless the Planning Authority gives written consent to any variation.
- Prior to works commencing the applicant is required to consult with the Department of Environment, Food and Agriculture regarding the possibility of bats and breeding birds within the gorse which are protected under the Wildlife Act 1993. No clearance of gorse should be undertaken during March to August inclusive.
- Any ventilation access cover, hand rail, cabinet or other structure (as shown on drawing 2117 REV C) which would be located above ground level, should be finished with a dark matt colour.
This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.
It was considered by the Planning Committee (02/09/10) that a further planning condition be attached to the approval which read as:-
C6. Any ventilation access cover, hand rail, cabinet or other structure (as shown on drawing 2117 REV C) which would be located above ground level, should be finished with a dark matt colour.