TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure) Order 2019
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Miss Lisa Samaras, Ref 25/90672/B, for the Additional use of workshop as occupational therapy facility at Lakeside Patrick Road St Johns Isle Of Man IM4 3BP .
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
Reason: To avoid an overly intensive use of the site that may require further consideration by the Department, in the interest of amenity and highway safety in the area.
on the land subject of the application, other than that expressly authorised by this approval, without the prior written approval of the Department.
Reason: The site is located in the countryside and the use is justified on the individual needs of the applicant, which would need to be reassessed should an alternative use be proposed.
Reason: The site is located in open countryside and the development is justified on the personal needs of the applicant only.
Reason: The site is located in the countryside and the use is justified on the individual needs of the applicant, which would need to be reassessed should an alternative use be proposed.
This decision relates to the following plans and drawings, date stamped 10 Jand 11 June 2025:
This decision has been made for the following reasons(s) The proposed development will make good use of an existing ancillary building, allowing the applicant to enhance their Occupational Therapy service to the benefit of the community and health services on the Island. The development will not give rise to any unacceptable impacts upon visual or residential amenity, or highway safety. The proposals are considered to comply with General Policy 2, Community Policy 6 and Transport Policy 7.
Date of Issue: 1st October 2025
J CHANCE Director of Planning and Building Control
Guidance Note
This decision was made by the Planning Committee in accordance with the authority delegated to it.
This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.
A copy of the Officer’s report and any correspondence which informed the assessment and decision is available to view on the Government’s website (via https://pbc.gov.im/onlineapplications/)
Implementation A determination to grant planning approval does not have effect —
Development must be carried out in accordance with the approved plans and any attached conditions (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Appeal Any appeal can only be made by a person who has been accorded rights to do so, must be in writing, include the appropriate fee and be submitted to the Department within 21 days of the date of this Notice.
Guidance on how to appeal is available at gov.im/howtoappeal