Loading document...
John Francis Moore Hillcrest, Balnahow Farm, Santon, IM4 1HN
TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure)(No 2) Order 2013
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by John Francis Moore, Ref 16/01084/B, for the Erection of agricultural barn in field 510984 at Field 510984 Balnahowe Santon Isle Of Man subject to compliance with the following condition(s) and notes (if any) :
Reason: To comply with article 14 of the Town and Country Planning (Development Procedure) (No2) Order 2013 and to avoid the accumulation of unimplemented planning approvals.
Reason: The building has been exceptionally approved solely to meet agricultural need and its subsequent retention would result in an unwarranted intrusion in the countryside.
REASON: the countryside is protected from development and an exception is being made on the basis of agricultural need. As such the building must be used for the purposes for which it is approved.
Reason: to minimise the visual impact of the development in the countryside which is generally protected from development. This approval relates to the drawings and plans received on 14th September, 2016. Date of Issue: 8th November 2016
Guidance Note
This decision was made by a Senior Planning Officer in accordance with the authority delegated to them in the name of the Minister and/or in the name and on behalf of the Department.
This permission refers only to that required under the The Town and Country Planning (Development Procedure)(No 2) Order 2013.
Any appeal against this decision must be in accordance with the criteria set down in that instrument.
Specifically, a valid appeal must be in writing, signed by the appellant, and submitted to the Department within 21 days of the date of this Notice. To further validate the appeal it must contain:
An appeal form and guidance notes are available from either Planning & Building Control, Tel 685950, or to download from the Department’s website https://www.gov.im/categories/planning-and-building-control/planningapplications/planning-appeals/how-to-appeal/
The proposed development must not be commenced until either;
Whichever is the later.
If no appeal is lodged within 21 days of the date of issue overleaf, and this decision becomes final, the Department’s public reference copy (counter copy) of the planning application may be collected by the applicant or their agent from Murray House.
A copy of the Officer’s report and any correspondence which led to the assessment and decision is now available to view on the Government’s website (via Online Services) or at the Department’s offices Murray House, Mount Havelock, Douglas.
https://www.gov.im/planningapplication/services/planning/search.iom
Please note that if the counter copy of the application is not collected within THIRTY DAYS following the last date on which a planning appeal can be made it will be destroyed without further notice.
Copyright in submitted documents remains with their authors. Request removal