Stephen Woodward 64 Wyborn Drive Onchan IM3 4AY
TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure) Order 2019
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Stephen Woodward, Ref 20/00304/C, for the Change of use from general industrial to leisure (Class 2.3 to class 4.4) at Unit C Balderton Court Balthane Ballasalla Isle Of Man IM9 2AJ .
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
Reason: to ensure that there is sufficient car parking to accommodate vehicles associated with the approved use.
This decision relates to drawings GA4, GA4A, GA5 and GA200 all received on 11th March, 2020.
This decision has been made for the following reasons(s) Whilst the proposed use is not consistent with the land use designation, it is considered that there is justification for accepting this alternative use as it supports the Strategic Plan objectives on recreation and it is not considered that there will be any environmental harm from the proposal.
Date of Issue: 7th May 2020
Guidance Note
This decision was made by the Planning Committee in accordance with the authority delegated to it.
This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.
A copy of the Officer’s report and any correspondence which led to the assessment and decision is available to view on the Government’s website (via Online Services www.gov.im/Viewapplications) or at the Department’s offices Murray House, Mount Havelock, Douglas.
Implementation The decision does not become final until either
Development must progress in accordance with the plans approved under, and any conditions attached to this approval (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Appeal Any appeal must be in writing and submitted to the Department within 21 days of the date of this Notice. The appeal must contain:
Failure to meet all of the relevant above requirements will mean that the appeal cannot be validated.
An appeal form and more detailed guidance are available either from Planning & Building Control, Tel 685950, or from the Department’s website www.gov.im/planningappeal
If this decision becomes final because there is no appeal, the Department’s public reference copy (counter copy) of the planning application may be collected by the applicant or their agent from Murray House. Please note that if the counter copy of the application is not collected within thirty days following the last date on which a planning appeal can be made it will be destroyed without further notice.