10 June 2020 · Committee
Ballacooiley, Dollagh, Ballaugh, Isle Of Man, IM7 5as
The proposal covers the change of use of agricultural fields to equestrian use for polo, along with a seasonal marquee erected annually from 1 April to 30 September and removed each winter. The site lies within an area of High Landscape Value and Scenic Significance on the Isle of Man, and is not designated for development, which meant the application was referred to the Planning Committee. Around 80 informal parking spaces are provided along the entrance drive. The key planning issues were the principle of equestrian use in a protected countryside setting, flood risk, impact on neighbours' living conditions, and highway safety. The site lies within a Flood Risk Area, but the marquee is only present in summer, no overnight sleeping is proposed, and bank reinforcement works by Manx Utilities have reduced flood risk. The officer concluded that the marquee has limited visual impact, the polo activity is an appropriate countryside use, and no significant harm to neighbours or highway safety would result.
The Planning Committee approved the application because polo and equestrian use is recognised as appropriate in the Isle of Man countryside under the Strategic Plan's equestrian policies, provided there is no significant harm to amenity, agricultural land, or highway safety. The officer found the marquee has limited visual impact, flood risk is adequately managed by its seasonal removal and existing bank reinforcement works, and the use would not cause unacceptable harm to neighbouring residents or road users.
safeguarding of the countryside for its own sake
The application is considered to accord with Environment Policies 1, 2, 10, 13, 19, 20, 21 and 22
Area Plan for the East sets out locally-applicable means for implementing the policies set out in the Isle of Man Strategic Plan 2016. In that Strategic Plan, we find the Environment Policies. Environment Policy 1 states: The countryside and its ecology will be protected for its own sake. For the purposes of this policy, the countryside comprises all land which is outside the settlements defined in Appendix 3 at A.3.6 or which is not designated for future development on an Area Plan. Development which would adversely affect the countryside will not be permitted unless there is an over- riding national need in land use planning terms which outweighs the requirement to protect these areas and for which there is no reasonable and acceptable alternative. Maintaining the purpose of this Area Plan as a means of implementation, there is some further direction to be found in the Strategic Plan, at paragraph 7.2.1: 'Whilst landscape and coastal change is inevitable, and in some cases desirable, the emphasis must be on the appropriateness of this change and the balance or equity between the needs of conservation and those of development. The primary goal must therefore be to respect, maintain and enhance the natural and cultural environment including nature conservation and landscape and coastal quality, and ensure its protection from inappropriate development.' Given the comprehensive nature of the Isle of Man Strategic Plan's Environmental Policies, only a small number of additional Proposals and Recommendations are necessary. In order to produce an implementable Area Plan for the East it is necessary to recognise those statutory desig nations and strategies which whilst having an Island-wide scope are highly relevant to the protection of environments within the Plan Area. An example is the UNESCO Biosphere status afforded to the Isle of Man. Island-level strategies identify crossborder issues and take account of the cumulative impacts of human engagement with nature. Area Plan Objectives i. To protect, conserve and enhance the natural and cultural environment of the plan area and promote biodiversity. ii. To improve the function, usability and provision of our green infrastructure and public spaces by providing a network of green spaces and features which are connected and where possible, accessible to the public. iii. To manage and improve flood risk and improve drainage conditions. iv. To support the working countryside and its custodians in maintaini ng a sustainable rural economy. Area Plan Desired Outcomes i. Where approved, d evelopment will be ecologically sustainable and designed to protect and where possible enhance biodiversity as well as mitigate and adapt to the effects of climate change. ii. The Green Infrastructure network will be established and fostered, connecting people with nature in a way that achieves the best shared outcomes for the urban and natural environment. iii. Statutory and non-statutory designations will continue to provide protection to the most important and most vulnerable cultural assets, habitats and environments in the plan area. iv. Beyond the towns and villages, the area as a whole will retain its landscape setting including its important visual interaction with the central uplands, central valley, coast and marine environment. Natural Environment Proposal 1 The Department supports the protection, creation and improvement of green infrastructure in the East, particularly in those locations which have the potential to be part of a Green Infrastructure Network. Applications for development must take into account any approved Government Green Infrastructure Strategies, but in any case, must identify how development proposals intend to contribute to the long term provision of a network of connected green spaces. UNESCO Biosphere In 2017, the Isle of Man became the first ever entire nation to achieve UNESCO Biosphere status. Project partners pledge to take steps to protect natural resources, develop the economy in a sustainable way and promote outstanding living landscapes. UNESCO Biosphere Reserves are established to connect people and the economy with nature, wildlife, culture, heritage and communities. Biosphere Reserves have three functions: Conservation: to contribute to the conservation of landscapes, ecosystems, species and genetic variation. Development: to foster economic and human development which is socio -culturally and ecologically sustainable. Logistic support: to support demonstration projects, environmental education and training, research and monitoring related to local, regional, national and global issues of conservation and sustainable development. The Isle of Man Biosphere is zoned into six areas . Examples of all of these can be found in the Eastern area: Terrestrial Core areas, Marine Core areas, Terrestrial Buffer zone, Marine Buffer zone, Terrestrial Transition areas and Marine Transition areas. There is some overlap with The Isle of Man's First Biodiversity Strategy 2015-20
protection of the character of the rural areas
The application is considered to accord with Environment Policies 1, 2, 10, 13, 19, 20, 21 and 22
d/Governor 's Road junction. Any future applications will be considered on their merits taking into account the proposals set out in this plan and the Strategic Plan (see Maps 3 and 6). Natural Environment Proposal 2 (Green Gap) Between the settlements of Douglas and Onchan in the area straddling Blackberry Lane, development which would erode the separation and detract from the openness between the settlements will not normally be supported. Applications may be considered favourably if reason for an exception can be demonstrated in line with General Policy 3(g). Laxey and Baldrine - Encroaching ribbon development along the A2 C oast Road which connects Laxey and Baldrine has the potential to connect the two settlements. At present this area largely retains its sense of being in the open countryside with clear sea views. Additionally, services for networked water supply and other essential utilities would be difficult to provide for additional development in this area (see Maps 3, 7 and 9). Natural Environment Proposal 3 (Green Gap) Between the settlements of Laxey and Baldrine, development which would erode the separation and detract from the openness between the settlements will not be supported. Glen Vine and Crosby - These two settlements, although proximate in location, are separate and distinct in many ways. Consultation has clearly demonstrated this through the views expressed during the stages of plan development. In cases such as this, the breaks in the urban fabric and the features of nature which provide a sense of openness should be protected from development which would erode this (see Maps 3 and 10). Natural Environment Proposal 4 (Green Gap) Between the settlements of Glen Vine and Crosby, development which would erode the separation and detract from the openness between the settlements is unlikely to be supported. Douglas, Union Mills and Strang (see Maps 3, 4 and 8) Natural Environment Proposal 5 (Green Gap) Between the settlements of and Douglas, Union Mills and Strang, development which would erode the separation and detract from the openness between the settlements is unlikely to be supported. The Upland Environment The Manx Uplands are an iconic part of our landscape and heritage. Reference to the 'sweet mountain air' and 'green hills and rocks' are enshrined in our national anthem and the colours of the heather and gorse are woven into the very fabric of Manx tartan. The hills are a place of great beauty, yet for some they are also a place to work and for others a place to exercise or simply enjoy open space. Our Uplands are also home to plants and animals that whilst familiar to us, are rare and impor tant in a global and European context. Furthermore, the uplands are a rich repository of cultural and archaeological remains, which are sensitive to change and can easily be damaged by inappropriate development. Production of food is an important and obvi ous function of hill land. But surprisingly, the Manx hills provide everyday functions that most people take for granted. Peatlands, which cover most of our hills reduce the impacts of climate change by locking up carbon dioxide, collect and filter our drinking water and slow the passage of rainfall into streams and rivers, thus reducing downstream flood risk. These multiple uses are of great benefit to the economy of the Isle of Man and the well - being of its people. It is important that the hills continue to provide these benefits long into the future. Ensuring sustainable management of such a wide range of uses to the satisfaction of all interested parties whilst retaining functions essential to the well -being of the Isle of Man is of paramount importance. The Isle of Man Government is the owner and landlord for the majority of the Uplands in the East region and is therefore in a position to implement policy which will deliver the optimum range of ecosystem services. Appropriate and positive Upland management such as controlled rotational burning/cutting of heather and low intensity grazing helps to reduce the fuel load of the hill, provides firebreaks and reduces the risk of unplanned wildfires that further protects the biodiversity of the site, but also the vast amounts of carbon locked away in the peat soils. The majority of this work is carried out by The Department of Environment, Food & Agriculture's grazing and shooting tenants. The Manx Uplands are critically important from a habitat and biodiversity perspective. The hills in the East support a significant number of breeding hen harriers; however, other native Upland breeding birds such as curlew and red grouse have suffered severe declines in recent decades and as such are of high conservation concern. Strict control of access and recreational activity on vulnerable soils should be implemented to reduce soil erosion and subsequent carbon loss. Curlew and hen harriers are recognised as an internationally important species, while (within the EU) upland heather moorland is designated
Condition 1
The marquee may be erected no earlier than 1st April in any year and retained until no later than 30th September in any year. Reason: to clarify the extent of the approval in relation to the content of the application.
Condition 2
The marquee may be used only for catering and hospitality associated with the holding of polo events on the site as defined in red in on plan reference 02. The site may not be used for these purposes for more than twelve days in total in any calendar year, of which no more than three days may be consecutive at any time. Reason: to clarify the extent of the approval having regard to the application and to the provisions of the Town and Country Planning (Permitted Development)(Temporary Uses) Order 2015.
Condition 3
If the marquee is no longer required or used for its approved purpose it must be removed from the site. Reason: in the interests of the character and appearance of the site and to prevent unwarranted structures remaining in areas not designated for development.
Condition 4
Prior to the erection of the marquee, an Event Management Plan shall be submitted to and approved in writing by the Department and the development shall be undertaken in accordance with this Plan. The Plan shall provide details of how events will be managed specifically how vehicles will enter, park and leave the site and how this will be marshalled. The applicant is encouraged to include information to welcome car sharing and sustainable methods of travelling to the site. Reason: to ensure free and safe use of the highway and to protect the living conditions of those in neighbouring properties.