15 October 2018 · Committee
Proposed Adventure Playground And Extension Of Public Open Space, Ballaughton Nurseries, Douglas, Isle Of Man, IM2 1ab
This application, submitted by Douglas Borough Council, sought permission to convert an unused nursery garden at Ballaughton Nurseries in Douglas into a public recreation space and adventure playground. The works included installing a shipping container, a log cabin, car parking, and boundary security fencing. The site was previously undeveloped and unused, and sits adjacent to existing public open space from which it is separated by a mature hedgerow and fencing. The Planning Committee considered the suitability of the proposed use, highway safety, and the effect on trees on or near the site. Permission was granted on 15 October 2018, subject to four conditions.
The Planning Committee approved the application on 15 October 2018. The key planning issues considered were whether the proposed use of the site was appropriate, highway safety, and the impact on existing trees. Permission was granted subject to four conditions.
General Policy 2
Development which is in accordance with the land-use zoning and proposals in the appropriate Area Plan and with other policies of this Strategic Plan will normally be permitted
General Policy 2: Development which is in accordance with the land-use zoning and proposals in the appropriate Area Plan and with other policies of this Strategic Plan will normally be permitted, provided that the development: (a) is in accordance with the design brief in the Area Plan where there is such a brief; (b) respects the site and surroundings in terms of the siting, layout, scale, form, design and landscaping of buildings and the spaces around them; (c) does not affect adversely the character of the surrounding landscape or townscape; (d) does not adversely affect the protected wildlife or locally important habitats on the site or adjacent land, including water courses; (e) does not affect adversely public views of the sea; (f) incorporates where possible existing topography and landscape features, particularly trees and sod banks; (g) does not affect adversely the amenity of local residents or the character of the locality; (h) provides satisfactory amenity standards in itself, including where appropriate safe and convenient access for all highway users, together with adequate parking, servicing and manoeuvring space; (i) does not have an unacceptable effect on road safety or traffic flows on the local highways; (j) can be provided with all necessary services; (k) does not prejudice the use or development of adjoining land in accordance with the appropriate Area Plan; (l) is not on contaminated land or subject to unreasonable risk of erosion or flooding; (m) takes account of community and personal safety and security in the design of buildings and the spaces around them; and (n) is designed having due regard to best practice in reducing energy consumption. 6.3 Development outside of areas zoned for development
Strategic Policy 5
New development, including individual buildings, should be designed so as to make a positive contribution to the environment of the Island.
Strategic Policy 5: New development, including individual buildings, should be designed so as to make a positive contribution to the environment of the Island. In appropriate cases the Department will require planning applications to be supported by a Design Statement which will be required to take account of the Strategic Aim and Policies. 4.4 Economy 4.4.1 The Spatial Strategy identifies the Major Employment Areas around the Island. While the majority of business and employment is focused around the Douglas Metropolitan Area, there are other major employment areas at Castletown, the Airport/Freeport, Peel, Ramsey and Jurby. The Department considers the distribution of employment areas provides a spread of employment opportunities around the Island. While recognising the opportunities for small scale local employment within existing centres it is considered new employment should, in the main, be concentrated within existing settlements or those major employment areas referred to in the Island Spatial Strategy and illustrated on the Key Diagram. Existing Local and new Area Plans will provide detailed boundar ies for these areas. From time to time Government may judge it appropriate to offer financial incentives to encourage economic activity or investment in particular parts of the Island.
Transport Policy 7
The Department will require that in all new development, parking provision must be in accordance with the Department's current standards.
Transport Policy 7: The Department will require that in all new development, parking provision must be in accordance with the Department's current standards. The current standards are set out in Appendix 7. 11.5.4 New development can have a significant impact in terms of the traffic generated by it and the impact on the various modes of travel. The Department considers that proposals which are likely to be significant traffic generators should be accompanied by a Transport Assessment(1) which should look at all modes of transport including access by public transport, cycling and on foot.
Recreation Policy 2
Development which would adversely affect, or result in the loss of Open Space or a recreational facility that is or has the potential to be, of recreational or amenity value to the community will not be permitted
Recreation Policy 2: Development which would adversely affect, or result in the loss of Open Space or a recreation facility that is or has the potential to be, of recreational or amenity value to the community will not be permitted except in the following circumstances: (a) where alternative provision of equivalent community benefit and of equivalent or better accessibility is made available; and (b) where there would be an overall com munity gain from the development, and the particular loss of the open space or recreation facility would have no significant unacceptable effect on local open space or recreation provision or on the character or amenity of the area. 10.3.6 In the case of residential developments for 10 or more dwellings, the Department proposes to adopt the following general standards (which refer to the area required per 1000 head of population): Recreational Open Space Sports Pitches 1.8 ha Children's Play Space 0.6 ha Amenity Space 0.8 ha 10.3.7 These general standards will be applied having regard to the following circumstances: (i) the size, type, and particular needs of the resident population in question; (ii) the needs of visitors to the area; and (iii) the proximity and availability of existing Open Space, including the foreshore, public glens and parks, and school fields which may be available for public use outside of school hours. More detail is set out in Appendix 6. 10.3.8 The Department has therefore adopted the following policy such as to plan positively for the provision of well-designed recreational and amenity space.
Condition 1
The development hereby approved shall be begun before the expiration of four years from the date of this decision notice.
Condition 2
Prior to occupation of the development, visibility splays of at least 2.4m x 17m in both directions must be provided at the car park entrance as shown on drawing no. E&R.17.007.1002 issue C, and retained as such thereafter with nothing above 1m in height within the visibility splay areas.
Condition 5
Prior to the commencement of works on the car park, details of the proposed surface and car park layout, as shown in drawing no. E&R.17.007.1002 issue C, shall be submitted to and approved in writing by the Department. The car park shall be provided in accordance with the approved details and made available for use prior to the first use of the adventure playground hereby permitted and shall be retained for use at all times thereafter.
Condition 6
The buildings and storage container hereby approved shall not be used other than for sport and leisure purposes in connection with the adventure playground. Should they no longer be required for the above purposes they shall be removed within two months of that time and the land restored in accordance with a scheme to be submitted to and approved in writing by the Department.